ProposedBig (AI-size): 700 megawatts

Glassworks Data Campus (former Owens-Illinois glass plant)

Also called: Glassworks

Local owners of the old glass plant in Clarion Borough are marketing it as a data center campus that could grow to 700 megawatts. It could use up to 1.2 million gallons of water a day from the Clarion River system. No tenant or formal plan has been announced.

👥 Reported, not confirmed yetSourceLast checked: Nov 2026

What happens next?

🗓️ Next meeting of the people who decide: Tuesday, December 1, 2026, 7:00 PM Eastern Time (local time)

Clarion Borough Council meeting

📍 Assembly Room of the Clarion Free Library.

Regular monthly meeting. The November meeting was Nov. 4. No data center item is listed.

The board meets on this day, but we don't know yet if this project is on the agenda. Call the office to check before you go.

Source

Where things stand: Proposed Concept plans only (January 2026). Developers say data centers are allowed 'by right'; county planning review would still be needed.

❓ 5 open questions about it: see below.

Last checked Nov 16, 2026.

🕒 Latest update (Jan 30, 2026): Concept plans made public: about 100 acres in phase 1 plus 85 more, up to 700 megawatts, up to 1.2 million gallons of water a day.

What we know

  • 📍 Where49 South Sheridan Drive, former Owens-Illinois glass plant, Clarion, Clarion County
  • 🏢 CompanyMiles Brothers, LLC
  • 🌳 Size185 acres
  • ⚡ Power it needs700 megawatts (about as much as 560,000 homes)
  • 🔌 Where the power comes from100 megawatts from FirstEnergy's West Penn substation now, growing to 700 megawatts with grid upgrades and possibly gas power on site
  • 💧 WaterPennsylvania American Water (Clarion River) · 1,200,000 gallons a day
  • ❄️ CoolingClosed-loop water systems (planned)
  • 👷 Jobs promised200

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has any data center company agreed to use the site? 🙋 I'll find out ·
  • Would a gas power plant be built on site? 🙋 I'll find out ·
  • How would 1.2 million gallons a day affect the Clarion River and local water customers? 🙋 I'll find out ·
  • What does Clarion Borough's January 2026 data center ordinance require? 🙋 I'll find out ·
  • Did the borough sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Jan 20, 2026
      Clarion Borough Council passed a data center ordinance.
    • Jan 30, 2026
      Concept plans made public: about 100 acres in phase 1 plus 85 more, up to 700 megawatts, up to 1.2 million gallons of water a day.

    Local votes and rules

    📜 Data center rules

    Clarion Borough Council voted 6-0 for Ordinance 2025-851. It allows data centers only in the Commercial and Industrial (CI) zone, keeping them out of neighborhoods. Council members called it a first step and said the county planning office would review any big project.

    Jan 20, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Is a massive data center coming to Clarion? Inside the conceptual plans for the 100-acre Glassworks Data Campus · exploreClarion · Jan 30, 2026
    2. Council Meetings · Clarion Borough · Oct 6, 2026
    3. U.S. Census Geocoder result for 49 South Sheridan Drive, Clarion, PA · U.S. Census Bureau · Oct 7, 2026
    4. OpenStreetMap map check · OpenStreetMap contributors · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.