๐Ÿงช Preview: Pennsylvania test version. Other states are being added.
๐Ÿ“ฃ Report Something
Being built

Nebius 'AI factory' at Highridge Industrial Park (Butler Township, Schuylkill)

Also called: Highridge Campus

Nebius, a Netherlands-based AI company, is building a large data center in the Highridge Industrial Park in Butler Township. It plans up to four data halls on about 600 acres and says it will invest $13-15 billion. About 37,000 gallons of water a day are approved for the site.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Phases 1 and 2 are under construction. Supervisors voted 2-1 in Aug./Sept. 2026 to rezone land for Phase 3.

๐Ÿ•’ Latest update (Sept 2026): Supervisors voted 2-1 to add land to the data center district for Phase 3, and lowered the noise limit to 65 decibels at the property line.

What we know

  • ๐Ÿ“ WhereHighridge Industrial Park, east side of Gordon Mountain Road, north of I-81; Phase 3 across the street next to the Walmart distribution center, Butler Township, Schuylkill County
  • ๐Ÿข CompanyNebius
  • ๐Ÿ‘ค Built forNebius (AI computing capacity not yet sold)
  • ๐ŸŒณ Size600 acres
  • โšก Power it needs1,200 megawatts (about as much as 960,000 homes)
  • ๐Ÿ”Œ Where the power comes fromPower from PPL Electric Utilities under a special agreement; Nebius says it pays for the power hookup. Batteries give about 30 minutes of backup power.
  • ๐Ÿ’ง WaterSchuylkill County Municipal Authority (Mount Laurel Reservoir) ยท 37,000 gallons a day
  • โ„๏ธ CoolingClosed-loop cooling
  • ๐Ÿ’ต Cost$13 billion
  • ๐Ÿ‘ท Jobs promised150

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

๐Ÿ”Ž What we checked

  • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits. The 37,000 gallons a day approved for the site by the water authority is water delivered; SRBC's limit counts only water that is used up, not all water delivered.

What happened so far

  • 2026
    Nebius bought land in the Highridge Industrial Park from NorthPoint for $187.5 million; site already zoned for data centers.
  • Aug 2026
    Open house: company said $13-15 billion investment, 1,000 construction jobs, 100-150 permanent jobs.
  • Aug 18, 2026
    Construction equipment working on Phases 1 and 2.
  • Sept 2026
    Supervisors voted 2-1 to add land to the data center district for Phase 3, and lowered the noise limit to 65 decibels at the property line.
  • Oct 2027
    Nebius's target for the first phase (about 260 megawatts) to start running. It plans to grow to 1,200 megawatts by late 2029.

Local votes and rules

๐Ÿ“œ Data center rules

Butler Township supervisors in Schuylkill County voted 3-0 for two data center ordinances. One rezoned land for a data center overlay of about 72 acres near Interstate 81 at Highridge Business Park. The other set rules for noise, fencing and cooling, and requires sound studies before and after building.

Sept 30, 2025
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

2018โ€“20202021โ€“2023
Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Butler supervisors clear hurdle for data center campus expansion at Highridge ยท The Shenandoah Sentinel ยท Sept 1, 2026
  2. Tech company discusses plans for 'AI factory' in Schuylkill County amid residents' concerns ยท WVIA ยท Aug 15, 2026
  3. Highridge Campus (Nebius, Butler Township) ยท More Than Just Parks Data Center Tracker
  4. PA DEP Data Center Permit Tracker ยท Pennsylvania DEP ยท Oct 6, 2026
  5. Highridge Business Park AI Factory ยท Nebius (company project page)
  6. Nebius contemplating 1.2 GW data center campus in Pennsylvania ยท W.Media ยท July 28, 2026
  7. Water Use by Data Centers in the Susquehanna River Basin - FAQ ยท Susquehanna River Basin Commission ยท 2026
  8. Water Application and Approval Viewer (WAAV) ยท Susquehanna River Basin Commission ยท Oct 6, 2026

See something wrong? Tell us and we'll fix it.