Proposed
Aliquippa data center and gas plant proposal (former J&L Steel mill site)
Also called: Five 9s Digital Aliquippa Data Center, Fezzik Energy Aliquippa
A local group called Fezzik Energy wants to put an AI data center and its own gas power plant on the old J&L steel mill land in Aliquippa. It says the city could get about $95 million in property tax over 10 years. No approvals have been found.
Where things stand: Announced idea with a planned 500 megawatt gas plant; no city approvals found.
๐ Latest update (2025): Developers said they hoped to start building on the old mill land later in 2025, with a 500 megawatt gas plant.
๐๏ธ Next meeting of the people who decide: Oct 7, 2026 ยท 7:00 PM
Aliquippa City Council meeting. We don't know yet if Aliquippa data center and gas plant proposal (former J&L Steel mill site) is on the agenda. Call the office to check before you go.
Aliquippa City Council meeting. We don't know yet if Aliquippa data center and gas plant proposal (former J&L Steel mill site) is on the agenda. Call the office to check before you go.
๐ Aliquippa City Hall. Next council work session listed: Nov. 18, 2026 at 7 p.m. at City Hall.
What we know
- ๐ WhereFormer J&L Steel mill slag heap along the Ohio River, Aliquippa, Beaver County
- ๐ข CompanyFezzik Energy (local partnership); Five 9s Digital named on tracker listings
- ๐ณ Size89 acres
- โก Power it needs500 megawatts (about as much as 400,000 homes)
- ๐ Where the power comes fromProposed 500 megawatt gas power plant on site
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has the developer filed any zoning or land development plans with the City of Aliquippa? ๐ I'll find out
- Who would own and use the data center? ๐ I'll find out
- Has DEP received an air permit application for the gas plant? ๐ I'll find out
- Where would water come from and how much per day? ๐ I'll find out
- Was a secret deal (NDA) signed with the city? ๐ I'll find out
What happened so far
- 2025Developers said they hoped to start building on the old mill land later in 2025, with a 500 megawatt gas plant.
๐ฐ๏ธ See it from above
Drag the slider to compare the land before and now.
2018โ20202021โ2023
We only know the town, so this shows the town center, not the exact site. Photos: PEMA / PASDA, Pennsylvania aerial photos.
Where this comes from
- Transforming Pittsburgh's old steel mills into an AI hub (discussion of Wall Street Journal article) ยท Scanalyst forum citing WSJ ยท 2025
- Five 9s Digital Aliquippa Data Center ยท Cleanview
- Beaver Valley becomes data center target ยท TMIA (reprint)
- Data center industry expands hopes in Western Pa., but its future remains uncertain ยท Tribune-Review / Mon Valley Independent ยท Aug 3, 2026