Status unclearBig (AI-size): 827 acres

Project Spring data center site north of Sand Springs

Also called: Project Spring

White Rose Partners wants to build a data center campus, reportedly backed by Google, on 827 acres north of Sand Springs. The city rezoned the land in Feb 2026. A land trust sued, saying part of the land is protected by a conservation easement.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Sand Springs City.

Where things stand: Status unclear Rezoned Feb 2026, but a lawsuit says a 2013 conservation easement bans industrial use on part of the land.

❓ 5 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (June 25, 2026): A court heard a motion to dismiss the lawsuit.

What we know

  • 📍 WhereNear N Highway 97 and Rock School Road (annexed from Osage County), Sand Springs, Osage County
  • 🏢 CompanyWhite Rose Partners
  • 👤 Built forGoogle (reported backer)
  • 🌳 Size827 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How will the court rule on the conservation easement lawsuit? 🙋 I'll find out ·
  • Is Google confirmed as the user? 🙋 I'll find out ·
  • Has the Osage Minerals Council agreed to any digging on the site? 🙋 I'll find out ·
  • How much water and power would it need? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • May 2025
      The landowners asked Sand Springs to annex the land.
    • Feb 3, 2026
      Sand Springs City Council voted 6-1 to rezone 827 acres for the data center.
    • March 24, 2026
      Land trust Land Legacy sued, saying a 2013 conservation easement bans industrial use.
    • June 25, 2026
      A court heard a motion to dismiss the lawsuit.

    Local votes and rules

    ⚖️ Court case

    Land trust Land Legacy sued the landowners, saying a 2013 conservation easement on about 270 of the 827 acres bans industrial use like a data center. A judge heard a motion to dismiss on June 24-25, 2026. As of September 2026 there was no ruling, and the project was on hold. A separate suit by the Protect Sand Springs Alliance was dismissed.

    March 24, 2026

    🗺️ Zoning change

    Sand Springs Planning Commission recommended the rezoning on January 27, 2026, with one no vote. On February 3, City Council voted 6-1 to rezone about 827 acres along Highway 97 from farm to light industrial use for the Project Spring data center, on land the city annexed from Osage County.

    Feb 3, 2026

    ⚖️ Court case

    A lawsuit by the resident group Protect Sand Springs Alliance over the Project Spring data center was dismissed by a Tulsa County district judge.

    2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.