DataOne / Nebius AI data center (East Vineland Industrial Park)

Also called: Nebius New Jersey, DataOne Vineland, LLC

DataOne is building a large AI data center in Vineland for Nebius, which sells computing power to Microsoft. It is planned to grow to 300 MW, about as much power as a mid-size city, and to make most of its own power with gas fuel cells. Many residents worry about noise, water and pollution.

✔ ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Phase 1 building is nearly done. Planning board approved the changed Phase 2 plan 8-1 on Aug. 17, 2026; state permits still needed. The city issued stop-work orders on fuel cells.

🕒 Latest update (Aug 17, 2026): Planning Board approved the changed Phase 2 plan 8-1 near midnight. No resident spoke in favor.

What we know

  • 📍 WhereFormer Silica Sands golf course area near 4031 South Lincoln Avenue, at Lincoln and Sheridan avenues (East Vineland Industrial Park), Vineland, Cumberland County
  • 🏢 CompanyDataOne Vineland, LLC
  • 🏛️ Owned byDataOne
  • 👤 Built forNebius (computing for Microsoft)
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
  • 🔌 Where the power comes fromMostly on-site Bloom Energy fuel cells that run on natural gas, with a 1.5-million-gallon liquefied natural gas (LNG) tank as backup.
  • 💧 WaterCity of Vineland water · 21,900 gallons a day
  • ❄️ CoolingChiller building, over 400 cooling fans and misting spray (WHYY)
  • 💸 Tax breaksThe city approved a payment-in-lieu-of-taxes (PILOT) deal in January 2026 (reported by Crypto Briefing).
  • 👷 Jobs promised200

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which state DEP permits (air, LNG tank) does the Phase 2 plan still need, and when will DEP decide? 🙋 I'll find out
  • Have the city's stop-construction orders on the fuel cells been lifted? 🙋 I'll find out
  • What exactly does the PILOT tax deal say, and how much will the company pay each year? 🙋 I'll find out

What happened so far

  • Aug 2024
    Vineland Planning Board first approved a large data center campus plan for the site (about 2.6 million sq ft in phases over up to 12 years).
  • March 2025
    Nebius announced an AI data center in Vineland with DataOne, growing in phases up to 300 MW.
  • July 2025
    Planning board approved an amended plan with DataOne as the applicant.
  • Jan 2026
    City approved a five-year PILOT tax deal for the project.
  • Feb 24, 2026
    An environmental impact statement was released, after construction had already begun.
  • Aug 5, 2026
    Vineland Planning Board special hearing at the Landis Theatre on the changed Phase 2 plan (a 587,980 sq ft building, fuel cell power areas, a chiller building, an LNG tank and a water treatment plant). No vote that night.
  • Aug 13, 2026
    City building officials issued a second stop-construction order, for Bloom fuel cells and an LNG tank put in without permits.
  • Aug 17, 2026
    Planning Board approved the changed Phase 2 plan 8-1 near midnight. No resident spoke in favor.

Local votes and rules

✅ Approved

Vineland's planning board voted 8-1, near midnight, to approve the changed second phase of the DataOne/Nebius AI data center. It includes Bloom fuel cells running on natural gas and a 1.5 million gallon LNG tank. State air permits are still needed. No resident spoke in favor.

Aug 17, 2026