1 data center project in Vineland City

Who decides here: the City Council of Vineland City votes on zoning. The Cumberland County may review big projects too.

In Vineland City

Nearby (within 15 miles)

Local votes and rules

βœ… Approved

Vineland's planning board voted 8-1, near midnight, to approve the changed second phase of the DataOne/Nebius AI data center. It includes Bloom fuel cells running on natural gas and a 1.5 million gallon LNG tank. State air permits are still needed. No resident spoke in favor.

Aug 17, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

What you can do

  1. Get told first.
    We'll email you if anything changes in Vineland City.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
πŸ“£ Report something here

πŸ”” Get told first

We'll email you when something changes in Vineland City. Nothing else.

⚑ Your electric company

Depending on where you live in Vineland City: City of Vineland (run by the town) or Atlantic City Electric Co. (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in New Jersey.

πŸ™‹ Open tasks here

  • Which state DEP permits (air, LNG tank) does the Phase 2 plan still need, and when will DEP decide?
  • Have the city's stop-construction orders on the fuel cells been lifted?
  • What exactly does the PILOT tax deal say, and how much will the company pay each year?