Approved, not built yetBig (AI-size): 108 megawatts

Bells Ferry Road data center campus (Grindcap / MMM Acquisitions)

Also called: Grindcap Marietta Campus, MMM Acquisitions Marietta

Grindcap plans two data center buildings (about 347,000 square feet, 108 megawatts) and a substation on a cell tower site off I-75 in Marietta. The city council approved the rezoning 7-0. Some neighbors worried about power bills.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Marietta City.

Where things stand: Approved, not built yet Marietta City Council approved the rezoning 7-0.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

What we know

  • 📍 Where1751 Bells Ferry Road, along I-75 (current cell tower site), Marietta, Cobb County
  • 🏢 CompanyMMM Acquisitions LLC
  • 🏛️ Owned byGrind Capital Group (Grindcap)
  • 🌳 Size31.437 acres
  • ⚡ Power it needs108 megawatts (about as much as 86,400 homes)
  • 🔌 Where the power comes fromClose to an existing power line; plans include a substation.
  • ❄️ Coolingclosed-loop cooling (reported)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    Local votes and rules

    ⏸️ Pause on new data centers

    Marietta City Council voted unanimously to extend its pause on new data center applications by one year. The pause was set to end Dec. 31, 2026, and now runs through Dec. 31, 2027. The council turned down an earlier idea to lift the pause.

    Nov 2026

    ✅ Approved

    Marietta City Council voted 5-2 to approve an 11-acre data center on Powers Ferry Place off Delk Road, after protests about noise, utility bills and home values. The city's pause did not apply because the developer, Prime Group Holdings, applied before it started.

    Aug 12, 2026

    ⏸️ Pause on new data centers

    Marietta City Council passed a pause on all new data center projects through December 31, 2026, and set aside a rezoning request for a data center on Powers Ferry Place. The pause did not cover applications already filed.

    July 8, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. 108MW data center campus granted zoning approval outside Atlanta, Georgia · Data Center Dynamics
    2. U.S. Census geocoder: 1751 Bells Ferry Road, Marietta, GA · U.S. Census Bureau · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.