Send us a tip
Stopped or cancelledBig (AI-size): 315 acres

Possible data center at Wayne Commerce Center in Jesup

Also called: Wayne Commerce Center

Wayne County's industrial development authority agreed to sell the 315-acre Wayne Commerce Center in Jesup, and a data center was a possible use. In October 2026 the buyer, SLT Ventures III, told the authority it was pulling out.

👥 Reported, not confirmed yetSourceLast checked: Nov 2026

What happens next?

Where things stand: Stopped or cancelled SLT Ventures III told the Wayne County Industrial Development Authority in October 2026 that it is pulling out of plans to buy the Wayne Commerce Center for a data center.

  • Oct 19, 2026: Our records now list Possible data center at Wayne Commerce Center in Jesup as stopped Source
  • Oct 6, 2026: Jesup, Wayne County: data center rules (ordinance) adopted Source

❓ 4 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Nov 2, 2026.

🕒 Latest update (Oct 2026): SLT Ventures III told the Wayne County Industrial Development Authority it is withdrawing from plans to buy the Wayne Commerce Center, which it had wanted for a data center.

What we know

  • 📍 WhereWayne Commerce Center industrial park in Jesup (315 acres), Jesup, Wayne County
  • 🏢 CompanySLT Ventures III (withdrew in October 2026)
  • 🌳 Size315 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Did the development authority sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
  • Is the site inside Jesup city limits, and which government's data center rules apply? 🙋 I'll find out ·
  • How much power and water would it use? 🙋 I'll find out ·
  • Will the Wayne County Industrial Development Authority offer the Wayne Commerce Center to another data center company? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 2026
      The Wayne County Industrial Development Authority approved a contract to sell the 315-acre Wayne Commerce Center, worth $23.6 million. A data center was named as a possible use.
    • Aug 17, 2026
      Wayne County commissioners held a public workshop; some said they had just learned of the sale.
    • Sept 2026
      Jesup commissioners voted 3-4 against a data center moratorium.
    • Oct 2026
      SLT Ventures III told the Wayne County Industrial Development Authority it is withdrawing from plans to buy the Wayne Commerce Center, which it had wanted for a data center.

    Local votes and rules

    📜 Data center rules

    Jesup commissioners voted 4-2 on Oct. 6, 2026 to approve the city's data center ordinance, the date set for its second reading. It allows data centers only as a conditional use in light industrial zones, with rules on noise and outdoor lighting and a water-saving cooling requirement. The mayor said he is drafting an amendment, which would need another hearing and vote. This updates the earlier first-reading record (ga-2026-jesup-ordinance).

    Oct 6, 2026

    📜 Data center rules

    Jesup city commissioners voted 4-2 on a first reading of an ordinance that defines data centers and allows them only as a conditional use in light industrial zones. Many residents asked for a full pause instead. A second reading was set for October 6, 2026 at 7 p.m.

    Sept 29, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something