Local votes and rules
📜 Data center rules · Jesup
Jesup commissioners voted 4-2 on Oct. 6, 2026 to approve the city's data center ordinance, the date set for its second reading. It allows data centers only as a conditional use in light industrial zones, with rules on noise and outdoor lighting and a water-saving cooling requirement. The mayor said he is drafting an amendment, which would need another hearing and vote. This updates the earlier first-reading record (ga-2026-jesup-ordinance).
📜 Data center rules · Jesup
Jesup city commissioners voted 4-2 on a first reading of an ordinance that defines data centers and allows them only as a conditional use in light industrial zones. Many residents asked for a full pause instead. A second reading was set for October 6, 2026 at 7 p.m.
Find your town
In Georgia, cities and towns decide inside their limits. Outside them, the county decides.