No project in Valencia Borough, but 3 nearby
Who decides here: the Borough Council of Valencia Borough votes on zoning. The Butler County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Misty Hollow Energy and Data Campus
Forward, Butler County
274 acres
🕒 Oct 22, 2026: The township planning commission cancelled its Oct. 22 meeting because the township engi…
Approved, not built yetabout 14 miles awaySpringdale Dynamo data center (former Cheswick power plant)
Springdale, Allegheny County
50 acres
🕒 Oct 28, 2026: Allegheny County held its second public meeting on the land development plan, in person …
Proposedabout 15 miles awayAliquippa data center and gas plant proposal (former J&L Steel mill site)
Aliquippa, Beaver County
89 acres
🕒 2025: Developers said they hoped to start building on the old mill land later in 2025, with a …
What you can do
- Get told first.
We'll email you if anything changes in Valencia Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
FirstEnergy Pennsylvania (formerly Penn Power) (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.