USA › New York › Rockland County

Rockland County

2 data center projects we know about. 23 villages and towns.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

Local votes and rules

⏸️ Pause on new data centers · Orangetown

Town board passed a 6-month pause on new data center and battery storage projects. It does not cover DataBank's planned Phase 2 expansion in Orangeburg, which is still under planning board review.

Aug 2026Source

📌 Other · Rockland County

County lawmakers passed a resolution asking the governor to sign the state bill for a one-year pause on large data centers. Supporters said it was the first county in New York to do so.

Aug 2026Source

📌 Other · Orangetown

Planning board ruled that DataBank's Phase 2 data center expansion must go through a full state environmental review (an environmental impact statement), as the company had asked to skip it.

July 8, 2026Source