Proposed

JPMorgan Chase data center expansion (Orangeburg)

JPMorgan Chase wants to add a second data center building to its campus in Orangeburg. The county development agency approved about $77 million in sales tax breaks, but the bank listed only one new permanent job. A state senator called it the biggest per-job subsidy in the nation.

πŸ‘₯ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Rockland County IDA approved about $77 million in sales tax breaks. News 12 said in April 2026 the town and the utility were still reviewing it.

πŸ•’ Latest update (2024): JPMorgan Chase asked Rockland County for tax help to expand its Orangeburg data center; the IDA approved about $77 million in sales tax breaks.

What we know

  • πŸ“ Where140 Old Orangeburg Road, Orangeburg (former Rockland Psychiatric Center land), Orangetown, Rockland County
  • 🏒 CompanyJPMorgan Chase
  • πŸ‘€ Built forJPMorgan Chase
  • πŸ’Έ Tax breaksAbout $77 million in sales tax exemptions approved by the Rockland County Industrial Development Agency.
  • πŸ‘· Jobs promised1

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2024
    JPMorgan Chase asked Rockland County for tax help to expand its Orangeburg data center; the IDA approved about $77 million in sales tax breaks.

Local votes and rules

⏸️ Pause on new data centers

Town board passed a 6-month pause on new data center and battery storage projects. It does not cover DataBank's planned Phase 2 expansion in Orangeburg, which is still under planning board review.

Aug 2026

πŸ“Œ Other

Planning board ruled that DataBank's Phase 2 data center expansion must go through a full state environmental review (an environmental impact statement), as the company had asked to skip it.

July 8, 2026
πŸ›°οΈ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. JPMorgan data center tax breaks spark debate in Rockland County Β· News 12 Westchester Β· April 23, 2026

See something wrong? Tell us and we'll fix it.