No project in Lonsdale City, but 2 nearby
Who decides here: the City Council of Lonsdale City votes on zoning. The Rice County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Archer Datacenters Faribault campus
Faribault, Rice County
84 acres
🕒 July 7, 2026: City Council gave Archer until March 31, 2027 to file a fuller environmental review (sup…
Stopped or cancelledabout 13 miles awayLakeville industrial site studied for a data center (Olam Holdings)
Lakeville, Dakota County
152 acres
🕒 May 27, 2026: A judge ruled the review was legal and said the data center talks are inactive.
Local votes and rules
⏸️ Pause on new data centers
Lonsdale paused data centers in the city for one year so it could study water and other effects. The vote was unanimous.
What you can do
- Get told first.
We'll email you if anything changes in Lonsdale City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Lonsdale City: Northern States Power Co. - Minnesota (company) or Steele-waseca Cooperative Electric (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Minnesota.