ProposedBig (AI-size): 120 megawatts

Archer Datacenters Faribault campus

Archer Datacenters wants to build up to 500,000 square feet of data centers on about 84 acres in Faribault's north industrial park, with up to 120 MW of power. In June 2026 the Court of Appeals said the city's environmental review was too weak. A new review is due by March 2027.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Faribault City.

Where things stand: Proposed An appeals court threw out the city's environmental review in June 2026. The city gave Archer until March 31, 2027 to file a fuller review.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (July 7, 2026): City Council gave Archer until March 31, 2027 to file a fuller environmental review (supplemental EAW).

What we know

  • 📍 Where15339 Acorn Trail, south of 150th St. W and east of I-35, Faribault, Rice County
  • 🏢 CompanyArcher Datacenters
  • 🌳 Size84 acres
  • ⚡ Power it needs120 megawatts (about as much as 96,000 homes)
  • 🔌 Where the power comes fromUp to 120 MW from a new substation on site.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will the Archer data center use, and how will it be cooled? 🙋 I'll find out ·
  • Which company will use the data center? 🙋 I'll find out ·
  • Will the city require a full environmental impact statement? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 2025
      MCEA appealed the city's decision to skip a full environmental impact statement.
    • June 8, 2026
      Minnesota Court of Appeals ruled the city's environmental review was not backed by enough evidence and sent it back.
    • July 7, 2026
      City Council gave Archer until March 31, 2027 to file a fuller environmental review (supplemental EAW).

    Local votes and rules

    📌 Other

    After the court ruling, Faribault's council gave the Archer data center until March 31, 2027 to finish a fuller environmental review. The project is a 500,000 square foot data center on about 87 acres.

    July 14, 2026

    ⚖️ Court case

    The Minnesota Court of Appeals ruled that Faribault's environmental review of a big data center did not follow state law. The city must redo a fuller review of water, energy, noise and effects on neighbors. The case was brought by the Minnesota Center for Environmental Advocacy.

    June 8, 2026

    🗺️ Zoning change

    Faribault's council approved a zoning change with clearer rules on where data centers can go in the city. In April it had put off a version that would have allowed them in heavy industrial zones.

    May 12, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. City of Faribault to revise environmental review after Minnesota Court of Appeals case · KEYC · June 10, 2026
    2. Faribault City Council directs supplemental EAW, extension to March 2027 · Faribault Daily News · July 2026
    3. Legal updates on MCEA's data center cases · Minnesota Center for Environmental Advocacy · May 15, 2026
    4. Data center site in Faribault fetches $4.5M · Faribault Daily News via Great River Energy · Nov 25, 2024
    5. Census geocoder: 15339 Acorn Trl, Faribault, MN 55021 · US Census Bureau · Oct 8, 2026