No project in St. John Town, but 6 nearby
Who decides here: the Town Council of St. John Town votes on zoning. The Lake County may review big projects too.
Nearby (within 15 miles)
Wylie Capital Broadway data center, Merrillville
Merrillville, Lake County
π June 1, 2026: A one-year town pause on new data center approvals started.
Reported in the news, not confirmed yet
Proposedabout 8 miles awayMerrillville Technology Park (Province Group)
Merrillville, Lake County
π June 1, 2026: A one-year town pause on new data center approvals started.
Reported in the news, not confirmed yet
Approved, not built yetabout 8 miles awayKaris Critical data center campus, Merrillville
Merrillville, Lake County
180 acres
π June 1, 2026: A one-year town pause on new data center approvals started.
Being builtabout 11 miles awayAmazon (AWS) Hobart data center campus
Hobart, Lake County
700 acres Β· for Amazon Web Services
π May 28, 2026: Merrillville officials said the Hobart campus was under construction.
Approved, not built yetabout 12 miles awayCoreWeave data center at Digital Crossroads, Hammond
Hammond, Lake County
25 acres Β· for CoreWeave
π Sept 29, 2025: The mayor said the $7 billion project was moving forward after NIPSCO got state approvalβ¦
Approved, not built yetabout 15 miles awaySentinel data center, Eagle Creek Township (near Lowell)
Eagle Creek Township, Lake County
160 acres
π June 9, 2026: Lake County Council approved rezoning 160 acres from farm to light industrial.
Reported in the news, not confirmed yet
Local votes and rules
π Data center rules Β· Lake County
Lake County adopted data center rules (Ordinance 2590). They include noise limits, setbacks, proof the power company has enough capacity, an energy efficiency plan, a water plan and a plan for taking the site down later.
What you can do
- Get told first.
We'll email you if anything changes in St. John Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Northern Indiana Pub Serv Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Indiana.