Send us a tip
Proposed

Merrillville Technology Park (Province Group)

Province Group proposed four data center buildings (1 million square feet total) near Colorado Street and Harms Road, worth up to $500 million. It only has early approval. The town paused new data center approvals until May 2027.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Town Council of Merrillville Town.

Where things stand: Proposed Got early approval from the town advisory committee in November 2024. On hold during the town's 2026-2027 pause.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (June 1, 2026): A one-year town pause on new data center approvals started.

What we know

  • 📍 WhereNear Colorado Street and Harms Road, Merrillville, Lake County
  • 🏢 CompanyProvince Group
  • 💵 Cost$500 million

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the Province Group project still active? 🙋 I'll find out ·
  • How many megawatts would it use? 🙋 I'll find out ·
  • Where exactly is the site, and how many acres? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: the pin is on the crossing of Colorado Street and Harms Road, as news describes.

    What happened so far

    • Nov 2024
      Merrillville's data center advisory committee gave early approval.
    • June 1, 2026
      A one-year town pause on new data center approvals started.

    Local votes and rules

    ⏸️ Pause on new data centers

    The town council paused approval of new data centers from June 1, 2026 to May 31, 2027. Four developers had approached the town.

    May 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. $2B in data center projects planned for Merrillville, Ind. · GovTech · Nov 25, 2024
    2. Data Centers · Town of Merrillville · 2026
    3. OpenStreetMap: Harms Road at Colorado Street, Merrillville · OpenStreetMap contributors · Oct 8, 2026