No project in East Chicago City, but 3 nearby
Who decides here: the City Council of East Chicago City votes on zoning. The Lake County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
CoreWeave data center at Digital Crossroads, Hammond
Hammond, Lake County
25 acres · for CoreWeave
🕒 Sept 29, 2025: The mayor said the $7 billion project was moving forward after NIPSCO got state approval…
Being builtabout 13 miles awayAmazon (AWS) Hobart data center campus
Hobart, Lake County
700 acres · for Amazon Web Services
🕒 May 28, 2026: Merrillville officials said the Hobart campus was under construction.
Approved, not built yetabout 15 miles awayAmazon (AWS) Portage data center
Portage, Porter County
for Amazon Web Services
🕒 Dec 5, 2023: Portage City Council approved tax breaks for the Amazon data center.
Local votes and rules
📜 Data center rules · Lake County
Lake County adopted data center rules (Ordinance 2590). They include noise limits, setbacks, proof the power company has enough capacity, an energy efficiency plan, a water plan and a plan for taking the site down later.
What you can do
- Get told first.
We'll email you if anything changes in East Chicago City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Northern Indiana Pub Serv Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Indiana.