USA โ€บ Indiana โ€บ Lake County โ€บ Hammond City
Approved, not built yet

CoreWeave data center at Digital Crossroads, Hammond

Also called: Data Center Peninsula, Digital Crossroad

Decennial Group plans a 450,000 square foot, 180 megawatt data center for AI company CoreWeave on the old State Line power plant site in Hammond. The city calls it the biggest project in its history, about $7 billion including computer equipment.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: City approved the development agreement in June 2025. Completion targeted for end of 2028.

๐Ÿ•’ Latest update (Sept 29, 2025): The mayor said the $7 billion project was moving forward after NIPSCO got state approval for its GenCo.

What we know

  • ๐Ÿ“ Where301 Digital Crossroads Drive (former State Line power plant site), Hammond, Lake County
  • ๐Ÿข CompanyDecennial Group
  • ๐Ÿ‘ค Built forCoreWeave
  • ๐ŸŒณ Size25 acres
  • โšก Power it needs180 megawatts (about as much as 144,000 homes)
  • ๐Ÿ”Œ Where the power comes fromNIPSCO power deal (through its new GenCo company).
  • ๐Ÿ’ต Cost$7 billion

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • June 9, 2025
    Hammond City Council voted 8-0 for the development agreement.
  • Sept 29, 2025
    The mayor said the $7 billion project was moving forward after NIPSCO got state approval for its GenCo.
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Hammond Approves Development Agreement for New Data Center ยท City of Hammond ยท June 9, 2025
  2. Plans for $7 billion data center moving forward, Hammond mayor says ยท Inside Indiana Business ยท Sept 29, 2025