No project in Forest Township, but 2 nearby
Who decides here: the Clinton County Board of Commissioners usually decides on zoning in Forest Township. Townships here have little say over land use.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Data One / Logistix data center proposal northwest of Frankfort
Clinton County
715 acres
🕒 Jan 20, 2026: County commissioners voted 3-0 to deny the rezoning.
Proposedabout 15 miles awayDigital Realty data center campus, Kokomo Industrial Park North
Kokomo, Howard County
476 acres
🕒 Oct 10, 2026: Digital Realty held a public open house about the plan.
Local votes and rules
✋ Turned down · Clinton County
County commissioners voted 3-0 to deny rezoning about 715 acres near Frankfort from farmland to light industrial for a data center by Data One. A similar request cannot come back for 12 months.
What you can do
- Get told first.
We'll email you if anything changes in Forest Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Duke Energy Indiana, LLC (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Indiana.