Data One / Logistix data center proposal northwest of Frankfort
Also called: Logistix Realty, Logix Realty LLC
A developer proposed a data center campus of about 715 acres northwest of Frankfort, using up to 300 megawatts and about 1 million gallons of water a day. County commissioners denied the rezoning in January 2026 after mostly negative public comments.
What happens next?
Where things stand: Stopped or cancelled County commissioners denied the rezoning 3-0 on Jan. 20, 2026. A similar request cannot come back for 12 months.
❓ 2 open questions about it: see below.
📣 See work going on anyway? Tell us
Last checked Oct 8, 2026.
🕒 Latest update (Jan 20, 2026): County commissioners voted 3-0 to deny the rezoning.
What we know
- 📍 WhereNorthwest of Frankfort, north and east of the Frito Lay and Conagra plants, Clinton County
- 🏢 CompanyData One (Logistix Realty)
- 🌳 Size715 acres
- ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
- 💧 Water1,000,000 gallons a day
- 💵 Cost$10 billion
- 👷 Jobs promised350
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will the developer try again after the 12-month wait? 🙋 I'll find out ·
- Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked for the exact site location but found no address, parcel or precise road description.
What happened so far
- July 2025Logistix withdrew its request to be annexed into Frankfort and moved the plan to the county.
- Jan 6, 2026Clinton County Area Plan Commission gave a favorable recommendation with conditions.
- Jan 20, 2026County commissioners voted 3-0 to deny the rezoning.
Local votes and rules
✋ Turned down
County commissioners voted 3-0 to deny rezoning about 715 acres near Frankfort from farmland to light industrial for a data center by Data One. A similar request cannot come back for 12 months.
Drag the slider to compare the land before and now.
Where this comes from
- Major data center project shifts focus from Frankfort to Clinton County · Inside Indiana Business · July 24, 2025
- 3-0 vote halts proposed data center rezoning in Clinton County · Frankfort Times · Jan 27, 2026
See something wrong? Tell us and we'll fix it.