Stopped or cancelledBig (AI-size): 300 megawatts

Data One / Logistix data center proposal northwest of Frankfort

Also called: Logistix Realty, Logix Realty LLC

A developer proposed a data center campus of about 715 acres northwest of Frankfort, using up to 300 megawatts and about 1 million gallons of water a day. County commissioners denied the rezoning in January 2026 after mostly negative public comments.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled County commissioners denied the rezoning 3-0 on Jan. 20, 2026. A similar request cannot come back for 12 months.

❓ 2 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (Jan 20, 2026): County commissioners voted 3-0 to deny the rezoning.

What we know

  • 📍 WhereNorthwest of Frankfort, north and east of the Frito Lay and Conagra plants, Clinton County
  • 🏢 CompanyData One (Logistix Realty)
  • 🌳 Size715 acres
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
  • 💧 Water1,000,000 gallons a day
  • 💵 Cost$10 billion
  • 👷 Jobs promised350

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the developer try again after the 12-month wait? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked for the exact site location but found no address, parcel or precise road description.

    What happened so far

    • July 2025
      Logistix withdrew its request to be annexed into Frankfort and moved the plan to the county.
    • Jan 6, 2026
      Clinton County Area Plan Commission gave a favorable recommendation with conditions.
    • Jan 20, 2026
      County commissioners voted 3-0 to deny the rezoning.

    Local votes and rules

    ✋ Turned down

    County commissioners voted 3-0 to deny rezoning about 715 acres near Frankfort from farmland to light industrial for a data center by Data One. A similar request cannot come back for 12 months.

    Jan 20, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Major data center project shifts focus from Frankfort to Clinton County · Inside Indiana Business · July 24, 2025
    2. 3-0 vote halts proposed data center rezoning in Clinton County · Frankfort Times · Jan 27, 2026

    See something wrong? Tell us and we'll fix it.