No project in Newark Village, but 5 nearby
Who decides here: the Village Board of Newark Village votes on zoning. The Kendall County may review big projects too.
Nearby (within 15 miles)
Plano Skies data center campus (Savion, off Rock Creek Road)
Plano, Kendall County
π 2026: Savion showed City Council a plan adding data center buildings to its solar project; aldβ¦
Reported in the news, not confirmed yet
Being builtabout 11 miles awayCyrusOne data center campus (Eldamain and Faxon roads, Yorkville)
Yorkville, Kendall County
228 acres
π July 9, 2024: Yorkville City Council approved the CyrusOne campus and a development agreement.
Approved, not built yetabout 12 miles awayProject Steel data center campus (Yorkville)
Yorkville, Kendall County
550 acres
π March 2026: Yorkville City Council approved annexation, a planned development and a development agreβ¦
Reported in the news, not confirmed yet
Approved, not built yetabout 12 miles awayProject Cardinal data center campus (Yorkville)
Yorkville, Kendall County
1,037 acres
π June 9, 2026: Developer asked the city to move its land-purchase deadline from July 1, 2026 to Dec. 31β¦
Proposedabout 14 miles awayMorris Technology Park (Tract, off I-80)
Morris, Grundy County
343 acres
π Jan 26, 2026: Tract bought 343 acres of farmland off I-80 for about $51.5 million.
What you can do
- Get told first.
We'll email you if anything changes in Newark Village. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Newark Village: Commonwealth Edison Co. (company) or Ameren Illinois Company (company) or Corn Belt Energy Corporation (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Illinois.