Built & runningBeing builtApproved, not built yetProposedStopped or cancelled
Local votes and rules
⏸️ Pause on new data centers · Americus
Americus City Council voted 5-1 for a 30-day pause on data centers so it can finish a data center ordinance. Liberty Data Centers plans a site in Frank Myers Industrial Park next to Georgia Southwestern State University. The city attorney warned against pausing for more than 180 days.
Sept 24, 2026Source
🤝 Agreement with the company · Americus
The local development authority sold a site in Frank Myers Industrial Park to Liberty Data Centers for $1 (fair market value $469,000). In return Liberty promised at least 150 full-time jobs averaging $80,000 a year, no private wells or sewer system, and limits on backup generator testing. If it breaks the deal it must pay back part or all of the land value.
July 1, 2026Source
Find your town
In Georgia, cities and towns decide inside their limits. Outside them, the county decides.