Projects
Rumble Technology Campus (Cloverleaf)
Unincorporated Monroe County, Monroe County
900 acres
🕒 July 25, 2025: Cloverleaf refiled to add about 325 acres to avoid wetlands (DRI #4515, later ended).
ProposedGoogle land for possible data center (Rumble Road)
Unincorporated Monroe County, Monroe County
950 acres · for Google
🕒 Sept 26, 2025: Google bought 950 acres for $58.5 million for a possible data center.
Reported in the news, not confirmed yet
Stopped or cancelledBolingbroke Technology Campus
Unincorporated Monroe County, Monroe County
900 acres
🕒 Aug 5, 2025: Monroe County Commission voted unanimously against the rezoning, a week after the planni…
Approved, not built yetForsyth Technology Campus (Trammell Crow)
Forsyth, Monroe County
1,632 acres
🕒 Feb 2, 2026: Forsyth City Council approved a conditional use permit 5-1; the permit can be revoked if…
Local votes and rules
✅ Approved · Forsyth
Forsyth City Council approved a conditional use permit for the Forsyth Technology Campus, a planned 12 million square foot data center on 1,600 acres west of I-75 Exit 193. The motion included safeguards, such as the chance to revoke the permit if plans do not move forward.
⏸️ Pause on new data centers · Unincorporated Monroe County
Monroe County paused new data center applications outside city limits in December 2025 while it reviews possible limits. Monroe County had already turned down one large data center rezoning in August 2025, while the city of Forsyth later approved another.
✋ Turned down · Unincorporated Monroe County
Monroe County commissioners voted unanimously against rezoning about 900 acres of mostly wooded land near Bolingbroke for a planned $5.8 billion data center. The planning board had also refused to recommend it. Hundreds of residents came to oppose it.
Find your town
In Georgia, cities and towns decide inside their limits. Outside them, the county decides.