No project in Meriden City, but 3 nearby
Who decides here: the City Council of Meriden City votes on zoning. The South Central Connecticut Planning Region may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Charter Development data center site off Barnes Road
Wallingford, South Central Connecticut Planning Region
26 acres
🕒 Dec 9, 2024: Wallingford Planning and Zoning Commission voted 4-1 to allow data centers in the Waters…
Reported in the news, not confirmed yet
Proposedabout 9 miles awayGlobal Common fuel cell data center campus on Geer Street (Cromwell)
Cromwell, Lower Connecticut River Valley Planning Region
159 acres
🕒 Oct 2026: News reports described Global Common's plan: about 40 MW first, growing to 300 MW or mor…
Proposedabout 12 miles awayReNew Riverside micro data center
Bristol, Naugatuck Valley Planning Region
1.62 acres
🕒 July 14, 2026: City Council asked the Zoning Commission to shrink the 250,000 sq ft data center size ca…
What you can do
- Get told first.
We'll email you if anything changes in Meriden City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Meriden City: Connecticut Light & Power Co. (company) or United Illuminating Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Connecticut.