ProposedBig (AI-size): 300 megawatts

Global Common fuel cell data center campus on Geer Street (Cromwell)

Also called: Global Common Cromwell

Global Common LLC wants to build a data center campus on about 159 acres on Geer Street in Cromwell, powered by fuel cells running on natural gas. It would start at about 40 MW and could grow to 300 MW or more. No application has been filed. The company says the zoning already allows it; the mayor says any application would still go through public hearings.

✔ ConfirmedSourceLast checked: Nov 1, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Town Council or Select Board of Cromwell Town.

Where things stand: Proposed No application filed yet. The company says it plans to seek site plan approval in early 2027.

❓ 5 open questions about it: see below.

Last checked Nov 1, 2026.

🕒 Latest update (Oct 2026): News reports described Global Common's plan: about 40 MW first, growing to 300 MW or more, on a site of about 159 acres. The company says the business park zoning allows a data center without a zone change.

What we know

  • 📍 Where76 Geer Street, next to Cromwell Middle School, Cromwell, Lower Connecticut River Valley Planning Region
  • 🏢 CompanyGlobal Common LLC
  • 🌳 Size159 acres
  • ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
  • 🔌 Where the power comes fromFuel cells on site, fed by natural gas from three Enbridge pipelines that cross the land (company's plan).

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • When will Global Common file its site plan, and will there be a public hearing? 🙋 I'll find out ·
  • How much water would the campus use, and where would it come from? 🙋 I'll find out ·
  • Did the town sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·
  • Who would use the data center? 🙋 I'll find out ·
  • What will the Planning and Zoning Commission decide on a resident's request (set for Dec. 3) to add data center rules to the zoning code? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Oct 2025
      Town records show the developer started talks with town staff in October 2025.
    • Sept 2026
      Cromwell Planning and Zoning Commission voted 5-2 against a one-year data center pause.
    • Oct 2026
      News reports described Global Common's plan: about 40 MW first, growing to 300 MW or more, on a site of about 159 acres. The company says the business park zoning allows a data center without a zone change.

    Local votes and rules

    ✋ Turned down

    After a public hearing, the commission voted down a proposed 12-month pause on data centers. It told town staff to write data center rules instead. There is no data center application in town.

    Sept 24, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Residents in Connecticut town fear giant-sized data center (from the Hartford Courant) · Government Technology / Hartford Courant · Oct 16, 2026
    2. Documents show Cromwell data center discussion dates back over a year · WFSB · Oct 23, 2026
    3. Are AI data centers coming to CT towns? Backlash and anxieties rise · CT Mirror · Oct 25, 2026
    4. Census geocoder: 76 Geer St, Cromwell, CT · US Census Bureau · Nov 1, 2026

    See something wrong? Tell us and we'll fix it.