Send us a tip
USA › Arizona › Pima County

Pima County

4 data center projects we know about. 6 towns, cities and unincorporated areas.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

Local votes and rules

🗺️ Zoning change · Unincorporated Pima County

Pima County's planning commission voted 8-1 to send the draft data center rules to the Board of Supervisors. Data centers would need a special permit with two public hearings and a supervisors' vote, and open-loop water cooling would be banned. The commission asked staff to tighten monitoring, noise and water limits first. Supervisors are expected to vote in early December, before the county's pause ends Jan. 20.

Oct 28, 2026Source

📜 Data center rules · Marana

Marana Town Council voted 5-1 for stricter data center rules. They add low-rumble (C-weighted) noise standards, bigger penalties for noise violations, steps for shutting a data center down later, and money up front from developers to cover that.

Oct 20, 2026Source

🗺️ Zoning change · Unincorporated Pima County

Pima County staff took public comments on Oct. 8 on draft data center rules. Data centers over 25 acres would only be allowed on heavy industry land (CI-2) and need a permit with two public hearings and a supervisors' vote. Open-loop water cooling would be banned. The planning commission hearing is set for Oct. 28; supervisors are expected to vote in December.

Oct 8, 2026Source

⏸️ Pause on new data centers · Pima County

County supervisors voted 3-2 to pause new data centers in unincorporated Pima County for 120 days, with a possible extension. It covers projects that had not yet applied for permits, so Project Blue and Project Gravel are not affected. The county is writing new zoning rules meanwhile.

Sept 23, 2026Source

📜 Data center rules · Tucson

City council voted 6-1 for strict rules on big data centers (over 25,000 square feet or over 20 megawatts). They must stay half a mile from homes, go through a full public rezoning process, and may not use drinking water for cooling. Rules took effect Sept. 4, 2026. The city is also looking at whether a full ban is legally possible.

Aug 5, 2026Source

🗳️ Public vote · Marana

Residents turned in about 2,800 signatures each on two petitions to let voters decide the data center rezoning. The town clerk rejected them because they were missing the right ordinances and land description. Beale sued the town over the petitions. In May 2026 a judge sided with the clerk, so there will be no public vote.

May 2026Source

⚖️ Court case · Pima County

The No Desert Data Center Coalition sued Pima County in January 2026, saying the public notice for the Project Blue rezoning hid what it was for, which they said broke the open meeting law. A judge threw out the case on April 13, 2026, ruling the county did not break the law.

April 13, 2026Source

🗺️ Zoning change · Marana

Town council voted unanimously to rezone two farm parcels on Luckett Road (about 600 acres) for a hyperscale data center by Beale Infrastructure. One member whose family owns a parcel did not vote. The planning commission had recommended it 6-0.

Jan 6, 2026Source

✋ Turned down · Tucson

City council voted unanimously to stop all work on Project Blue and drop the plan to bring the 290-acre site into the city. The project later moved ahead outside city limits.

Aug 6, 2025Source

✅ Approved · Pima County

County supervisors approved the rezoning and the sale of county land for Project Blue, a large data center near the Pima County Fairgrounds.

June 17, 2025Source

📜 Data center rules · Marana

Town council passed Ordinance 2024.029. Very large (hyperscale) data centers need a special rezoning (specific plan), must meet design and noise rules, and must show they have enough power and water.

Dec 2024Source

Find your town

In Arizona, cities and towns decide inside their limits. Outside them, the county decides.