ProposedBig (AI-size): 160 acres

Project Gravel data center (west of Sahuarita)

Also called: Project Gravel

A landowner plans eight data center buildings (about 203,000 square feet each) and a power substation on about 160 acres of empty desert west of Sahuarita, on a former chemical plant site. Papers in the plan aim for full build-out by 2029. The user and the power and water needs are not public.

✔ ConfirmedSourceLast checked: Oct 13, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Pima County Board of Supervisors (for land outside city and town limits).

Where things stand: Proposed Plans for eight buildings are with Pima County. KJZZ reports the county's 120-day pause does not apply because the plan came in first. No public hearing or approval yet.

❓ 5 open questions about it: see below.

Last checked Oct 13, 2026.

🕒 Latest update (Oct 9, 2026): County staff said it is not decided whether the new data center rules would apply to Project Gravel.

What we know

  • 📍 Whereabout 2480 W. Twin Buttes Rd., just west of Sahuarita town limits (two of three parcels), Unincorporated Pima County, Pima County
  • 🏢 CompanySahuarita Holdings, LLC (landowner)
  • 🏛️ Owned byW.R. Henderson Construction (per state corporation filings, Arizona Daily Star)
  • 🌳 Size160 acres
  • 🔌 Where the power comes fromTucson Electric Power, with a new substation on site (Green Valley News)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who will run or use the data center? 🙋 I'll find out ·
  • How much power and water would it use? 🙋 I'll find out ·
  • What permit has been filed with Pima County, and when? 🙋 I'll find out ·
  • Will Pima County's new data center rules apply to this project? 🙋 I'll find out ·
  • Did the county sign an agreement to keep the plans private (NDA)? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 22, 2026
      News reports said plans for eight data center buildings on about 160 acres west of Sahuarita had reached Pima County staff.
    • Sept 23, 2026
      Pima County passed a 120-day pause on new data centers; KJZZ reported Project Gravel is exempt.
    • Oct 9, 2026
      County staff said it is not decided whether the new data center rules would apply to Project Gravel.

    Local votes and rules

    🗺️ Zoning change

    Pima County's planning commission voted 8-1 to send the draft data center rules to the Board of Supervisors. Data centers would need a special permit with two public hearings and a supervisors' vote, and open-loop water cooling would be banned. The commission asked staff to tighten monitoring, noise and water limits first. Supervisors are expected to vote in early December, before the county's pause ends Jan. 20.

    Oct 28, 2026

    🗺️ Zoning change

    Pima County staff took public comments on Oct. 8 on draft data center rules. Data centers over 25 acres would only be allowed on heavy industry land (CI-2) and need a permit with two public hearings and a supervisors' vote. Open-loop water cooling would be banned. The planning commission hearing is set for Oct. 28; supervisors are expected to vote in December.

    Oct 8, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.