1 data center project in Unincorporated Powhatan County
Who decides here: the Powhatan County Board of Supervisors decides on zoning for land outside city and town limits.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Unincorporated Powhatan County
Nearby (within 15 miles)
Google Project Skye (4201 Moseley Road, near Magnolia Green)
Chesterfield County, Chesterfield County
850 acres · for Google
🕒 2025: County zoning approval, before Google was publicly named.
Reported in the news, not confirmed yet
Proposedabout 12 miles awayTract Tuckahoe Tech Park (west of West Creek)
Goochland County, Goochland County
900 acres
🕒 Oct 20, 2026: Goochland Circuit Court heard the county's request to dismiss the lawsuit over the Techn…
Reported in the news, not confirmed yet
Proposedabout 12 miles awayGoogle data center campus in West Creek Business Park
Goochland County, Goochland County
1,000 acres · for Google
🕒 Oct 28, 2026: The county announced that Google is the company looking at the West Creek site; Google c…
Reported in the news, not confirmed yet
Approved, not built yetabout 13 miles awayGoogle Project Loch (750 Watkins Centre Parkway)
Chesterfield County, Chesterfield County
350 acres · for Google
🕒 2025: County zoning approval.
Reported in the news, not confirmed yet
Local votes and rules
🗺️ Zoning change
Supervisors unanimously rezoned about 60 acres for the Powhatan Technology Park by Newport Equities. With about 120 acres rezoned before, the data center campus totals about 180 acres in eastern Powhatan.
What you can do
- Get told first.
We'll email you if anything changes in Unincorporated Powhatan County. - Go to county meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Unincorporated Powhatan County: Virginia Electric & Power Co. (company) or Southside Electric Co-op, Inc. (co-op (owned by its members)) or Central Virginia Electric Co-op (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.
🙋 Open tasks here
- Who will use it, and how much water and power will it need?
- When will Vantage file a site plan, and how many megawatts will the campus use?