ProposedBig (AI-size): 5,344 acres

Site Layer 4 data center campus northeast of Wheatland (Goshen Hole)

Also called: Goshen Hole

A company called Site Layer 4 wants to build a large data center campus with its own power plant on 5,344 acres of ranch land northeast of Wheatland. A $26 billion figure has been mentioned. The land is now zoned industrial, but the project still needs a special use permit.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Platte County Commissioners (for land outside city and town limits).

Where things stand: Proposed County rezoned the ranch land to industrial on Sept. 2, 2026. A special use permit is still needed.

❓ 4 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Sept 2, 2026): County commissioners unanimously approved the rezoning with four conditions, including a return to ranch zoning if building doesn't start within five years.

What we know

  • 📍 WhereRanch land in Goshen Hole, northeast of Wheatland near the Goshen County line, about 13 miles east of I-25, Unincorporated Platte County, Platte County
  • 🏢 CompanySite Layer 4, LLC
  • 🌳 Size5,344 acres
  • 🔌 Where the power comes fromLarge power plant built on the site. Type not yet stated.
  • 💧 Waternot city water or the Wheatland Irrigation District (company)
  • ❄️ Coolingclosed-loop cooling
  • 👷 Jobs promised300

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is behind Site Layer 4, and who would use the data center? 🙋 I'll find out ·
  • What kind of power plant would be built, and how big? 🙋 I'll find out ·
  • When will the county hear the special use permit? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the news reports and the 2020 state parcel map for an exact site: none gives a parcel, address or road corner.

    What happened so far

    • July 2026
      Site Layer 4 asked to rezone 5,344 acres from ranch to industrial use.
    • Aug 26, 2026
      Platte County Planning and Zoning Commission unanimously recommended the rezoning.
    • Sept 2, 2026
      County commissioners unanimously approved the rezoning with four conditions, including a return to ranch zoning if building doesn't start within five years.

    Local votes and rules

    🗺️ Zoning change

    County commissioners unanimously rezoned 5,344 acres of ranch land in Goshen Hole, northeast of Wheatland, to industrial for a planned data center. Any use still needs a special use permit. The land goes back to ranch zoning if building does not start within five years.

    Sept 2, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Ranchlands Near Wheatland Eyed For $26 Billion 'Transformational' Data Center · Cowboy State Daily · July 13, 2026
    2. Platte County Recommends Rezoning Private Ranchland For Proposed Data Center · Cowboy State Daily · Aug 27, 2026
    3. Platte County Commissioners Push Back, Then OK Industrial Zoning For Data Center · Cowboy State Daily · Sept 2, 2026

    See something wrong? Tell us and we'll fix it.