Proposed

Possible Cloverleaf data center (Wrightstown)

Also called: Cloverleaf Wrightstown

Wrightstown leaders talked with Cloverleaf Infrastructure about a possible data center starting in January 2026. Cloverleaf said it could be similar in size to the first phase of Port Washington. No plan has been filed, the village has a 12-month pause, and most voters said no in an advisory vote.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Village Board of Wrightstown Village.

Where things stand: Proposed No formal plan has been filed and Cloverleaf has not bought land. The village paused data center planning for 12 months, and voters rejected data centers in an August 2026 advisory vote.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Aug 11, 2026): In a non-binding vote, 85.8% of Wrightstown voters said no to village support for large data centers.

What we know

  • 📍 WhereWrightstown, Brown County
  • 🏢 CompanyCloverleaf Infrastructure

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where exactly was Cloverleaf looking for land around Wrightstown? 🙋 I'll find out ·
  • Has Cloverleaf stopped looking in Wrightstown after the August vote? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Jan 2026
      Emails from public records show the village administrator began talking with Cloverleaf.
    • May 26, 2026
      Cloverleaf leaders attended a village listening session; many residents spoke against a data center.
    • July 2026
      The Village Board extended its pause (moratorium) on data center planning to 12 months.
    • Aug 11, 2026
      In a non-binding vote, 85.8% of Wrightstown voters said no to village support for large data centers.

    Local votes and rules

    🗳️ Public vote

    Wrightstown voters said no, 1,033 to 151, when asked if the village should provide utilities and other public help for a large data center. The vote was advisory, so it does not legally bind the Village Board.

    Aug 11, 2026

    ⏸️ Pause on new data centers

    Wrightstown's Village Board paused data center planning in June 2026, then unanimously turned it into a one-year pause in July, ahead of the August vote by residents.

    July 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something