Stopped or cancelledBig (AI-size): 500 acres

Cassville data center proposal (Grant County)

An unnamed company looked at about 500 acres near Cassville for a $1 billion-plus data center needing 400-500 megawatts. The town banned data centers for up to two years, and the proposal fell apart.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

Where things stand: Stopped or cancelled The town voted to ban data centers in April 2026 and the developer stopped responding.

❓ 2 open questions about it: see below.

📣 See work going on anyway? Tell us

Last checked Oct 8, 2026.

🕒 Latest update (June 2026): Reports said the developer had stopped returning calls and the plan was all but dead.

What we know

  • 📍 WhereNear the Cardinal-Hickory Creek power line in the town of Cassville, Cassville, Grant County
  • 🏢 Companyunknown
  • 🌳 Size500 acres
  • 💵 Cost$1 billion
  • 👷 Jobs promised50
  • 🤐 Privacy agreement (NDA)No

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which company was behind the Cassville proposal? 🙋 I'll find out ·
  • Where exactly is the site? A parcel number, address or agenda link helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 2025
      The Grant County Economic Development Corp. made the proposal public.
    • April 16, 2026
      Town of Cassville voters took on zoning powers, and the town moved to ban data centers for up to 2 years.
    • June 2026
      Reports said the developer had stopped returning calls and the plan was all but dead.

    Local votes and rules

    ⏸️ Pause on new data centers

    Town of Cassville residents voted to give the town board zoning power, and the board adopted a rule that bans data centers in the town for up to two years, or until the town writes zoning. It came after an unnamed developer floated a $1 billion, roughly 500-acre data center.

    April 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Another billion-dollar Wisconsin data center is eyed for Cassville in Grant County · Wisconsin Watch · Feb 9, 2026
    2. Rural town of Cassville rejects data center plan · Wisconsin Watch · April 29, 2026
    3. How a Driftless Area data center deal fell apart · Urban Milwaukee / Wisconsin Watch · June 23, 2026

    See something wrong? Tell us and we'll fix it.