Cassville data center proposal (Grant County)
An unnamed company looked at about 500 acres near Cassville for a $1 billion-plus data center needing 400-500 megawatts. The town banned data centers for up to two years, and the proposal fell apart.
Where things stand: The town voted to ban data centers in April 2026 and the developer stopped responding.
π Latest update (June 2026): Reports said the developer had stopped returning calls and the plan was all but dead.
What we know
- π WhereNear the Cardinal-Hickory Creek power line in the town of Cassville, Cassville, Grant County
- π’ Companyunknown
- π³ Size500 acres
- π΅ Cost$1 billion
- π· Jobs promised50
- π€ Secret deal (NDA)No
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which company was behind the Cassville proposal? π I'll find out
What happened so far
- Dec 2025The Grant County Economic Development Corp. made the proposal public.
- April 16, 2026Town of Cassville voters took on zoning powers, and the town moved to ban data centers for up to 2 years.
- June 2026Reports said the developer had stopped returning calls and the plan was all but dead.
Local votes and rules
βΈοΈ Pause on new data centers
Town of Cassville residents voted to give the town board zoning power, and the board adopted a rule that bans data centers in the town for up to two years, or until the town writes zoning. It came after an unnamed developer floated a $1 billion, roughly 500-acre data center.
An aerial photo of the area.
Where this comes from
- Another billion-dollar Wisconsin data center is eyed for Cassville in Grant County Β· Wisconsin Watch Β· Feb 9, 2026
- Rural town of Cassville rejects data center plan Β· Wisconsin Watch Β· April 29, 2026
- How a Driftless Area data center deal fell apart Β· Urban Milwaukee / Wisconsin Watch Β· June 23, 2026