Solis Arx data center campus at Progress Park

A new company, Solis Arx, is building an AI data center campus on 99 acres at Progress Park. The county expects over $1 billion in investment and more than $10 million a year in taxes by 2028. The company says it will use about 2,000 gallons of water a day.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Wythe County Board of Supervisors (for land outside city and town limits).

Where things stand: Being built Announced December 2025; site work has started at Progress Park.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Dec 16, 2025): Solis Arx named Cadence as its general contractor.

What we know

  • 📍 Where99-acre lot in Progress Park, Wythe County, Wythe County
  • 🏢 CompanySolis Arx
  • 🌳 Size99 acres
  • 🔌 Where the power comes fromAppalachian Power
  • 💧 WaterTown of Wytheville · 2,000 gallons a day
  • ❄️ Coolingclosed-loop and air-based cooling
  • 💵 Cost$1 billion
  • 💸 Tax breaksThe county gave the Progress Park lot at no cost.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts will the Solis Arx campus use? 🙋 I'll find out ·
  • How many permanent jobs will Solis Arx create? 🙋 I'll find out ·
  • Which lot in Progress Park is the 99-acre Solis Arx site? A parcel number or site plan helps. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 5, 2025
      Wythe County announced the Solis Arx data center at Progress Park.
    • Dec 16, 2025
      Solis Arx named Cadence as its general contractor.

    Local votes and rules

    🗺️ Zoning change

    The planning commission voted 5-2 to send the county's first zoning ordinance and map to supervisors. Data centers would need a special exception permit, with a public hearing and a board vote, and would be allowed only in commercial and industrial zones. The two data centers already planned would not be affected. Supervisors hold a public hearing on December 3, 2026 at Wytheville Community College. The suggested start date is July 1.

    Nov 2026

    📜 Data center rules

    Wythe County has no countywide zoning. Its first draft zoning ordinance would require a special use permit and a public hearing for data centers. In September 2026 the county was collecting public comments before formal hearings.

    Sept 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Details released on Wythe County data center projects' water usage, tax revenues · Cardinal News · Dec 16, 2025
    2. Wythe County lands major digital infrastructure investment at Progress Park · WVVA · Dec 5, 2025