Project Tallmadge (Takanock, Strasburg Industrial Park)
Takanock plans a data center campus on more than 80 acres in the Strasburg Industrial Park near I-81. Data centers were allowed there without a hearing when it bought the land. A revised plan in 2026 shrank it to two buildings with 120 MW of computing load, down from 320 MW.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Town Council of Strasburg Town.
Where things stand: Proposed Allowed by current zoning; the town is reviewing a revised site plan (August 2026).
❓ 2 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (Aug 2026): Revised site plan cut computing load to 120 MW.
What we know
- 📍 WhereStrasburg Industrial Park near I-81, Strasburg, Shenandoah County
- 🏢 CompanyTakanock
- 🌳 Size80 acres
- ⚡ Power it needs120 megawatts (about as much as 96,000 homes)
- ❄️ Coolingclosed-loop cooling
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water and total power will it use? 🙋 I'll find out ·
- Will the town approve the site plan? 🙋 I'll find out ·
What happened so far
- Jan 2025First site plan showed two buildings at 160 MW each.
- Aug 2026Revised site plan cut computing load to 120 MW.
Drag the slider to compare the land before and now.
Where this comes from
- Revised Tallmadge plan shrinks data center buildings · Northern Virginia Daily · Aug 6, 2026
- Strasburg residents raise concerns over proposed data center spanning 80-acre parcel · WHSV · May 28, 2026
See something wrong? Tell us and we'll fix it.