Vantage VA4 data center campus
Vantage Data Centers plans to spend $2 billion on three data centers (929,000 square feet, 192 MW) on 82 acres in Stafford County. It plans closed-loop chilled water cooling.
Where things stand: Announced November 2025; first building due late 2027.
๐ Latest update (Nov 6, 2025): Vantage announced the VA4 campus.
What we know
- ๐ WhereStafford County, Stafford County
- ๐ข CompanyVantage Data Centers
- ๐ณ Size82 acres
- โก Power it needs192 megawatts (about as much as 153,600 homes)
- โ๏ธ Coolingclosed-loop chilled water
- ๐ต Cost$2 billion
- ๐ท Jobs promised50
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Exactly where is the site? ๐ I'll find out
What happened so far
- Nov 6, 2025Vantage announced the VA4 campus.
Local votes and rules
๐ Data center rules
After a meeting that ran past 2:30 a.m., supervisors voted 4-2 (one abstaining) to require data center buildings to sit at least 750 feet from homes, schools, and the Rappahannock and Potomac rivers, up from 100 feet. County staff called it the strictest setback in Virginia.
Oct 22, 2025
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Vantage Data Centers to Invest $2B for New Campus in Northern Virginia ยท REBusinessOnline ยท Nov 10, 2025
See something wrong? Tell us and we'll fix it.