Proposed

Yondr and Cerberus 72 MW campus (Manassas area)

Yondr and Cerberus bought a 40-acre site to build a 72 MW data center campus in the Manassas area. They expect it to open in 2029.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Prince William County Board of Supervisors (for land outside city and town limits).

Where things stand: Proposed Land bought in 2026; due to open in 2029.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Aug 3, 2026): Yondr and Cerberus announced they bought the 40-acre site.

What we know

  • 📍 WherePrince William County, Prince William County
  • 🏢 CompanyYondr Group
  • 🏛️ Owned byCerberus Capital Management (funds)
  • 🌳 Size40 acres
  • ⚡ Power it needs72 megawatts (about as much as 57,600 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Exactly where is the site, and is it inside the City of Manassas or the county? 🙋 I'll find out ·
  • Does it need a rezoning or public hearing? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 3, 2026
      Yondr and Cerberus announced they bought the 40-acre site.

    Local votes and rules

    🗺️ Zoning change

    Supervisors unanimously shrank the Data Center Opportunity Zone Overlay District from about 9,700 to 3,500 acres. Most new data centers will now need a special use permit with a public hearing. Projects already filed get a 90-day grace period.

    Sept 22, 2026

    ✋ Turned down

    Supervisors voted 8-0 to reject a land-use plan change for the Dulles South Innovation Center, a proposed campus of about 43 million square feet of data centers on 1,940 acres of homes and farms near Sanders Lane (Gainesville District).

    July 7, 2026

    ⚖️ Court case

    Neighbors sued over the county's December 2023 rezoning for the 2,100-acre Prince William Digital Gateway. A judge voided it because the newspaper notices were not spaced far enough apart, and the Court of Appeals agreed on March 31, 2026. The county stopped defending it in April, and QTS dropped its last appeal on July 2, 2026, ending the project.

    March 31, 2026

    📜 Data center rules

    Supervisors voted 5-2 to update the noise law so data center cooling systems must meet noise limits around the clock: 73 decibels by day and 68 at night, measured on the 'C' scale that captures low hum. Residents and the county's advisory group had asked for a stricter method.

    Oct 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025