Data center on Prince William Parkway near Hornbaker Road
Also called: Innovation Town Center
Supervisors voted 4-3 to allow a 571,000-square-foot data center and another large building on a narrow 40-acre site along Prince William Parkway near Hornbaker Road. The area was taken out of the county's data center zone in 2019.
Where things stand: Supervisors approved it 4-3 in March 2026, outside the county's data center zone.
π Latest update (March 3, 2026): Board of County Supervisors approved the project 4-3.
What we know
- π WhereAlong Prince William Parkway near Hornbaker Road, Prince William County, Prince William County
- π³ Size40 acres
β Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the developer and who will use the data center? π I'll find out
What happened so far
- March 3, 2026Board of County Supervisors approved the project 4-3.
Local votes and rules
πΊοΈ Zoning change
Supervisors unanimously shrank the Data Center Opportunity Zone Overlay District from about 9,700 to 3,500 acres. Most new data centers will now need a special use permit with a public hearing. Projects already filed get a 90-day grace period.
β Turned down
Supervisors voted 8-0 to reject a land-use plan change for the Dulles South Innovation Center, a proposed campus of about 43 million square feet of data centers on 1,940 acres of homes and farms near Sanders Lane (Gainesville District).
βοΈ Court case
Neighbors sued over the county's December 2023 rezoning for the 2,100-acre Prince William Digital Gateway. A judge voided it because the newspaper notices were not spaced far enough apart, and the Court of Appeals agreed on March 31, 2026. The county stopped defending it in April, and QTS dropped its last appeal on July 2, 2026, ending the project.
π Data center rules
Supervisors voted 5-2 to update the noise law so data center cooling systems must meet noise limits around the clock: 73 decibels by day and 68 at night, measured on the 'C' scale that captures low hum. Residents and the county's advisory group had asked for a stricter method.
An aerial photo of the area.
Where this comes from
- Supervisors OK data center outside of the county's overlay Β· Prince William Times Β· March 4, 2026