STACK Infrastructure data center campus at Berry Hill megasite

Also called: Berry Hill Data Center, Southern Virginia Megasite at Berry Hill

STACK Infrastructure plans a huge AI data center campus on nearly 3,000 acres at the Berry Hill megasite west of Danville. The company talks about $100 billion over 30 years and 2,500 jobs. Some residents asked for more public input first.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: County supervisors backed the plan in July 2026. STACK bought most of the megasite; full build-out could take 15 to 30 years.

πŸ•’ Latest update (July 21, 2026): Pittsylvania County supervisors passed a resolution supporting the data center campus.

What we know

  • πŸ“ WhereSouthern Virginia Megasite at Berry Hill, less than 10 miles west of Danville, Pittsylvania County, Pittsylvania County
  • 🏒 CompanySTACK Infrastructure
  • 🌳 Size3,000 acres
  • πŸ’§ WaterRecycled water and some Dan River water; no well water, officials say
  • πŸ’΅ Cost$100 billion
  • πŸ’Έ Tax breaksThe 2026 state budget gives a sales tax break on equipment until at least 2040 (maybe 2050) if STACK invests $35 billion and creates 1,000+ jobs paying 1.5 times the local wage. The land sale (about $238,000 an acre) is split between Danville and Pittsylvania County. STACK must pay at least $48.5 million a year in local taxes.
  • πŸ‘· Jobs promised2,500

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • April 2026
    STACK Infrastructure bought nearly 3,000 acres of the Berry Hill megasite.
  • May 18, 2026
    The Danville-Pittsylvania Regional Industrial Facilities Authority approved the performance agreement with STACK.
  • June 30, 2026
    The General Assembly finished a state budget with a tax break written for this project.
  • July 21, 2026
    Pittsylvania County supervisors passed a resolution supporting the data center campus.

Local votes and rules

πŸ—ΊοΈ Zoning change

Supervisors unanimously rezoned the Southern Virginia Mega Site at Berry Hill so data centers that meet the code can be built by right, without public hearings. Some residents objected.

Jan 15, 2026

βœ‹ Turned down

Supervisors voted 6-1 to deny Balico's rezoning of about 750 acres near Chatham for a data center campus and gas power plant. Earlier the same night they voted 5-2 not to let Balico withdraw the request.

April 15, 2025

πŸ—ΊοΈ Zoning change

Supervisors unanimously rezoned about 946 acres in Ringgold to heavy industrial (M-2) for Anchorstone Advisors' planned data center campus of $1 billion or more.

July 16, 2024
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.