Approved, not built yetBig (AI-size): 200 megawatts

Anchorstone data center campus in Ringgold (Route 58 East)

Also called: Route 58 East Data Center Campus

A developer got 946 acres in the Ringgold area rezoned for a data center campus in 2024. It was described as a $1 billion-plus project with 200 megawatts to start. No company has said it will use it.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Pittsylvania County Board of Supervisors (for land outside city and town limits).

Where things stand: Approved, not built yet Supervisors rezoned 946 acres to heavy industrial in July 2024. No tenant named; no construction reported yet.

❓ 3 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (July 16, 2024): Pittsylvania County supervisors voted unanimously to rezone 946 acres for heavy industry for a data center campus.

What we know

  • 📍 WhereRinggold area, with direct access to U.S. Route 58, Pittsylvania County, Pittsylvania County
  • 🏢 CompanyAnchorstone Advisors SOVA
  • 🌳 Size946 acres
  • ⚡ Power it needs200 megawatts (about as much as 160,000 homes)
  • 💵 Cost$1 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is the end user of the Ringgold data center campus? 🙋 I'll find out ·
  • Has the data center use permit from the Board of Zoning Appeals been granted? 🙋 I'll find out ·
  • Has construction started in Ringgold? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 16, 2024
      Pittsylvania County supervisors voted unanimously to rezone 946 acres for heavy industry for a data center campus.

    Local votes and rules

    🗺️ Zoning change

    Supervisors unanimously rezoned the Southern Virginia Mega Site at Berry Hill so data centers that meet the code can be built by right, without public hearings. Some residents objected.

    Jan 15, 2026

    ✋ Turned down

    Supervisors voted 6-1 to deny Balico's rezoning of about 750 acres near Chatham for a data center campus and gas power plant. Earlier the same night they voted 5-2 not to let Balico withdraw the request.

    April 15, 2025

    🗺️ Zoning change

    Supervisors unanimously rezoned about 946 acres in Ringgold to heavy industrial (M-2) for Anchorstone Advisors' planned data center campus of $1 billion or more.

    July 16, 2024
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. $1 billion data center campus moves forward in Pittsylvania · Virginia Business · Sept 29, 2024