STACK / Silver Companies campus, Celebrate Virginia South
Right after Fredericksburg made a 250-acre technology zone where data centers are allowed without a hearing, The Silver Companies and STACK announced a possible $10 billion plan for 8 to 12 data centers in Celebrate Virginia South. It still needs a water agreement with the city and new power lines from Dominion.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Fredericksburg City.
Where things stand: Proposed City created a 250-acre technology zone in 2025. Full buildout depends on a water deal and new Dominion power lines.
❓ 2 open questions about it: see below.
Last checked Oct 10, 2026.
🕒 Latest update (Feb 25, 2025): City Council advanced the Technology Overlay District on first reading.
What we know
- 📍 WhereCelebrate Virginia South area, north end of the city, Fredericksburg, Fredericksburg city
- 🏢 CompanySTACK Infrastructure and The Silver Companies
- 🌳 Size250 acres
- 🗼 New power linesYes
- 💵 Cost$10 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has the city signed a water agreement? 🙋 I'll find out ·
- Where will Dominion's new power lines run? 🙋 I'll find out ·
What happened so far
- Feb 25, 2025City Council advanced the Technology Overlay District on first reading.
Local votes and rules
🗺️ Zoning change
After a 5.5-hour meeting, city council unanimously created a Technology Overlay District that allows data centers by right in Celebrate Virginia South, starting with the 63-acre NEON property (up to about 2.5 million square feet). The planning commission had recommended denial 4-3.
Drag the slider to compare the land before and now.
Where this comes from
- The Silver Companies and STACK planning $10 billion data center investment in the city · Fredericksburg Free Press · Feb 26, 2025
- The Silver Companies and STACK Infrastructure announce agreement to build data centers in Fredericksburg · City of Fredericksburg · Feb 2025
- Fredericksburg approves technology overlay district, paving the way for data centers · Potomac Local · Feb 26, 2025
See something wrong? Tell us and we'll fix it.