EdgeCore Culpeper campus (Culpeper Technology Zone)
EdgeCore bought 120 acres in Culpeper's technology zone in 2024 for a 1.4 million-square-foot data center campus. Power is to come from Rappahannock Electric Cooperative starting in early 2028.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Culpeper County Board of Supervisors (for land outside city and town limits).
Where things stand: Being built Land bought July 2024; first power from Rappahannock Electric Cooperative expected early 2028.
❓ 1 open question about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (July 2024): EdgeCore bought 120 acres in the Culpeper Technology Zone.
What we know
- 📍 WhereCulpeper Technology Zone, listed at 15650 Nalles Mill Road, next to the town wastewater plant, Culpeper County, Culpeper County
- 🏢 CompanyEdgeCore Digital Infrastructure
- 🏛️ Owned byPartners Group
- 🌳 Size120 acres
- 🔌 Where the power comes fromRappahannock Electric Cooperative
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts will it use, and will new power lines be needed? 🙋 I'll find out ·
What happened so far
- July 2024EdgeCore bought 120 acres in the Culpeper Technology Zone.
Local votes and rules
🗺️ Zoning change
Supervisors now require a conditional use permit (with a public hearing) for all new data centers on industrial land outside the Culpeper Tech Zone. Before, they were allowed there by right.
Drag the slider to compare the land before and now.
Where this comes from
- EdgeCore secures $1.5B toward Sterling data centers construction · Virginia Business · April 22, 2026
- EdgeCore Culpeper Campus (15650 Nalles Mill Rd) · Datacentermap · Oct 8, 2026
- EdgeCore plans 216MW data center campus in Virginia's Culpeper County · DatacenterDynamics · 2024
- Census geocoder: 15650 Nalles Mill Rd · US Census Bureau · Oct 8, 2026
See something wrong? Tell us and we'll fix it.