Send us a tip
Being builtBig (AI-size): 120 acres

EdgeCore Culpeper campus (Culpeper Technology Zone)

EdgeCore bought 120 acres in Culpeper's technology zone in 2024 for a 1.4 million-square-foot data center campus. Power is to come from Rappahannock Electric Cooperative starting in early 2028.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Culpeper County Board of Supervisors (for land outside city and town limits).

Where things stand: Being built Land bought July 2024; first power from Rappahannock Electric Cooperative expected early 2028.

❓ 1 open question about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (July 2024): EdgeCore bought 120 acres in the Culpeper Technology Zone.

What we know

  • 📍 WhereCulpeper Technology Zone, listed at 15650 Nalles Mill Road, next to the town wastewater plant, Culpeper County, Culpeper County
  • 🏢 CompanyEdgeCore Digital Infrastructure
  • 🏛️ Owned byPartners Group
  • 🌳 Size120 acres
  • 🔌 Where the power comes fromRappahannock Electric Cooperative

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts will it use, and will new power lines be needed? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 2024
      EdgeCore bought 120 acres in the Culpeper Technology Zone.

    Local votes and rules

    🗺️ Zoning change

    Supervisors now require a conditional use permit (with a public hearing) for all new data centers on industrial land outside the Culpeper Tech Zone. Before, they were allowed there by right.

    Sept 2, 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. EdgeCore secures $1.5B toward Sterling data centers construction · Virginia Business · April 22, 2026
    2. EdgeCore Culpeper Campus (15650 Nalles Mill Rd) · Datacentermap · Oct 8, 2026
    3. EdgeCore plans 216MW data center campus in Virginia's Culpeper County · DatacenterDynamics · 2024
    4. Census geocoder: 15650 Nalles Mill Rd · US Census Bureau · Oct 8, 2026