Ladysmith Data Hub (18577 Green Road)
A data center campus with a 10-acre substation is proposed on 140 acres on Green Road, off U.S. 1 just west of I-95 near Ladysmith. Neighbors spoke against it. The Planning Commission recommended denial because it does not fit the county plan.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Caroline County Board of Supervisors (for land outside city and town limits).
Where things stand: Proposed Planning Commission voted 4-2 in July 2025 to recommend denial; supervisors decide.
❓ 2 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (July 24, 2025): Planning Commission voted 4-2 to recommend denial of the special exception permit.
What we know
- 📍 Where18577 Green Road, off U.S. Route 1, Ladysmith, Caroline County, Caroline County
- 🌳 Size140.3 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Did the Board of Supervisors approve or deny it? 🙋 I'll find out ·
- Who is the developer? 🙋 I'll find out ·
What happened so far
- July 24, 2025Planning Commission voted 4-2 to recommend denial of the special exception permit.
Drag the slider to compare the land before and now.
Where this comes from
- Caroline Planning Commission recommends denial of Ladysmith Data Hub after residents speak out · Fredericksburg Free Press · July 28, 2025
- Census geocoder: 18577 Green Rd · US Census Bureau · Oct 8, 2026