Proposed
Amazon Mattameade data center campus (I-95 and Mudd Tavern Road)
Also called: Mattermeade Tech Campus
Amazon wants to build 11 two-story data center buildings on about 1,143 acres southeast of I-95 and Mudd Tavern Road, on land in both Caroline and Spotsylvania counties. Its permit papers say the campus could reach at least 770 MW and include three substation pads and a water treatment plant.
Where things stand: Amazon applied for federal and state wetlands permits in February 2025.
๐ Latest update (Feb 2025): Amazon sent a joint wetlands permit application to the U.S. Army Corps of Engineers.
What we know
- ๐ WhereSoutheast of the I-95 and Mudd Tavern Road interchange (also in Spotsylvania County), Caroline County, Caroline County
- ๐ข CompanyAmazon Data Services
- ๐๏ธ Owned byAmazon
- ๐ค Built forAmazon Web Services
- ๐ณ Size1,143 acres
- โก Power it needs770 megawatts (about as much as 616,000 homes)
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Have the county and the Army Corps approved it? ๐ I'll find out
- Where would the water come from? ๐ I'll find out
- How many acres are in Caroline and how many in Spotsylvania? ๐ I'll find out
What happened so far
- Feb 2025Amazon sent a joint wetlands permit application to the U.S. Army Corps of Engineers.
๐ฐ๏ธ See it from above
An aerial photo of the area.
We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.
Where this comes from
- Amazon eyes Caroline, Spotsylvania for 11-building data center campus ยท Virginia Business ยท Feb 20, 2025