AVAIO Digital data center campus at Appomattox Center for Business and Commerce

AVAIO Digital bought 452 acres in the county industrial park for a $3 billion data center campus using 300 megawatts. The company says it could bring over $65 million in new taxes. Neighbors say there was little public input.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: The county sold the 452 acres in 2024; the land was already zoned for data centers. First building planned for 2027-2028.

๐Ÿ•’ Latest update (March 23, 2026): AVAIO told the county authority it plans the first building and part of a substation in 2027-2028.

What we know

  • ๐Ÿ“ WhereAppomattox Center for Business and Commerce, off U.S. 460 and Route 26 north of the town of Appomattox, Appomattox County, Appomattox County
  • ๐Ÿข CompanyAVAIO Digital Partners
  • ๐ŸŒณ Size452 acres
  • โšก Power it needs300 megawatts (about as much as 240,000 homes)
  • ๐Ÿ”Œ Where the power comes fromCentral Virginia Electric Cooperative and Dominion Energy (300 megawatts), plus a new substation on site
  • ๐Ÿ’ต Cost$3 billion
  • ๐Ÿ‘ท Jobs promised250

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Dec 10, 2024
    The county economic development authority agreed to sell 452 acres to AVAIO for about $4.5 million.
  • Feb 24, 2026
    Nearby residents raised concerns; no work on the land had begun.
  • March 23, 2026
    AVAIO told the county authority it plans the first building and part of a substation in 2027-2028.

Local votes and rules

๐Ÿค Agreement with the company

Supervisors approved a performance agreement with AVAIO Digital for 'Project Hercules', a $3 billion data center campus on more than 400 acres in the county industrial park just outside the town of Appomattox.

Aug 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Appomattox County strikes deal for data center ยท Cardinal News ยท Dec 11, 2024
  2. Appomattox County answers questions for future data center ยท WDBJ ยท March 23, 2026
  3. Appomattox residents concerned about planned data center ยท WDBJ ยท Feb 24, 2026