AVAIO Digital data center campus at Appomattox Center for Business and Commerce
AVAIO Digital bought 452 acres in the county industrial park for a $3 billion data center campus using 300 megawatts. The company says it could bring over $65 million in new taxes. Neighbors say there was little public input.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Appomattox County Board of Supervisors (for land outside city and town limits).
Where things stand: Approved, not built yet The county sold the 452 acres in 2024; the land was already zoned for data centers. First building planned for 2027-2028.
❓ 3 open questions about it: see below.
Last checked Oct 12, 2026.
🕒 Latest update (Oct 5, 2026): The developer said construction should start by the end of 2026, with first power in 2027. State regulators approved the stormwater plan. About 50 megawatts is available now; more needs new power lines from the electric co-op and Dominion.
What we know
- 📍 WhereAppomattox Center for Business and Commerce, off U.S. 460 and Route 26 north of the town of Appomattox, Appomattox County, Appomattox County
- 🏢 CompanyAVAIO Digital Partners
- 🌳 Size452 acres
- ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
- 🔌 Where the power comes fromCentral Virginia Electric Cooperative and Dominion Energy (300 megawatts), plus a new substation on site
- 💧 WaterTown of Appomattox (up to 45,000 gallons a day of water and the same of wastewater; more needs town approval)
- 💵 Cost$3 billion
- 👷 Jobs promised250
- 🤐 Privacy agreement (NDA)Yes. The county economic development authority signed an agreement to keep the plans private (NDA) about three years ago, a news report says.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much water will the Appomattox data center use per day? 🙋 I'll find out ·
- Will new power lines be built for the Appomattox campus? 🙋 I'll find out ·
- Will the county sign a tax deal (performance agreement) for this campus, and what does it say? 🙋 I'll find out ·
What happened so far
- Dec 10, 2024The county economic development authority agreed to sell 452 acres to AVAIO for about $4.5 million.
- Feb 24, 2026Nearby residents raised concerns; no work on the land had begun.
- March 23, 2026AVAIO told the county authority it plans the first building and part of a substation in 2027-2028.
- Oct 5, 2026The developer said construction should start by the end of 2026, with first power in 2027. State regulators approved the stormwater plan. About 50 megawatts is available now; more needs new power lines from the electric co-op and Dominion.
Local votes and rules
🤝 Agreement with the company
Supervisors approved a performance agreement with AVAIO Digital for 'Project Hercules', a $3 billion data center campus on more than 400 acres in the county industrial park just outside the town of Appomattox.
Drag the slider to compare the land before and now.
Where this comes from
- Appomattox County strikes deal for data center · Cardinal News · Dec 11, 2024
- Appomattox County answers questions for future data center · WDBJ · March 23, 2026
- Appomattox residents concerned about planned data center · WDBJ · Feb 24, 2026
- Virginia statewide parcels (VGIN): 453-acre Appomattox County parcel north of U.S. 460 · Virginia Geographic Information Network · Oct 8, 2026
- Project Hercules data center construction expected to start by end of the year in Appomattox County · Cardinal News · Oct 5, 2026
See something wrong? Tell us and we'll fix it.