Old Dominion Capital Partners data center (Madison Heights)
Old Dominion Capital Partners filed plans for five data center buildings and an electric substation on about 40 acres of a 93-acre lot behind the former Big Lots on Business 29 in Madison Heights. The same day, supervisors changed the county's data center zoning rules.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Amherst County Board of Supervisors (for land outside city and town limits).
Where things stand: Proposed The county said the August 2026 application was incomplete. The developer must now get a special exception, with Planning Commission and Board of Supervisors hearings.
❓ 3 open questions about it: see below.
Last checked Oct 26, 2026.
🕒 Latest update (Sept 2026): The county said the application was incomplete. Any new filing needs a special exception from the Board of Supervisors, with public hearings first.
What we know
- 📍 WhereBehind the former Big Lots on Business 29, Madison Heights, Amherst County, Amherst County
- 🏢 CompanyOld Dominion Capital Partners LLC
- 🌳 Size93 acres
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- When will the public hearings be? 🙋 I'll find out ·
- How much power and water would it use? 🙋 I'll find out ·
- Will Old Dominion Capital Partners file a new application for a special exception? 🙋 I'll find out ·
What happened so far
- Aug 18, 2026Developer filed its application; supervisors changed data center zoning rules the same day.
- Sept 2026The county said the application was incomplete. Any new filing needs a special exception from the Board of Supervisors, with public hearings first.
Local votes and rules
🗺️ Zoning change
Supervisors voted 3-2 to require a special use permit for future data centers, so residents get a public hearing before a decision.
Drag the slider to compare the land before and now.
Where this comes from
- Developer files application to bring data center to heart of Madison Heights · WSET · Aug 31, 2026
- Data center plan behind the Seminole shopping center · The News & Advance · Oct 8, 2026
- Nominatim: Seminole Plaza, Madison Heights · OpenStreetMap Nominatim · Oct 8, 2026
- Virginia statewide parcels (VGIN): Amherst parcels 156-1-6 and 156-1-2,3,4A,5,C · Virginia Geographic Information Network · Oct 8, 2026
- Amherst County data center application faces special exception process · WSET · Sept 30, 2026
See something wrong? Tell us and we'll fix it.