BluSky AI modular data center in Nephi
Also called: BluSky AI Nephi
BluSky AI plans a small (4 MW) modular data center on leased land in Nephi. The deal is not final.
Where things stand: Non-binding letter of intent to lease land, signed September 2025.
๐ Latest update (Sept 23, 2025): BluSky AI announced a non-binding deal to lease about 16,000 sq ft for a 4 MW modular data center.
What we know
- ๐ Where1358 N 200 W, Nephi, Nephi, Juab County
- ๐ข CompanyBluSky AI Inc.
- โก Power it needs4 megawatts (about as much as 3,200 homes)
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Was the lease signed and has the city approved the site? ๐ I'll find out
What happened so far
- Sept 23, 2025BluSky AI announced a non-binding deal to lease about 16,000 sq ft for a 4 MW modular data center.
Local votes and rules
๐ Data center rules
Nephi's city council created a new Industrial 4 (ID4) zone just for data centers and their power plants (Ordinance 12-02-2025). Data centers must use air cooling or closed-loop cooling, not open evaporative cooling. Power plants must bring their own water rights. The zone sets lot size, setbacks, height and dark-sky lighting rules.
An aerial photo of the area.
Where this comes from
- BluSky AI looks to lease land in Utah for 4MW data center site ยท DatacenterDynamics ยท Sept 2025
- BluSky AI press release (Exhibit 99.1) ยท SEC EDGAR ยท Sept 23, 2025