QTS data center campus in Eagle Mountain
Also called: QTS Salt Lake City 1
QTS is building a five-building data center campus on about 193 acres in Eagle Mountain, next to Meta. The city says the buildings will not use water for cooling.
Where things stand: Construction started in October 2024. The third building was topped out in April 2026.
๐ Latest update (April 2026): The third building was topped out.
What we know
- ๐ WhereWest of the Meta campus, Eagle Mountain, Eagle Mountain, Utah County
- ๐ข CompanyQTS Data Centers
- ๐๏ธ Owned byBlackstone
- ๐ณ Size193 acres
- โ๏ธ Coolingcooling that does not use water (per the city)
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts will the full campus use? ๐ I'll find out
- Which companies will use it? ๐ I'll find out
What happened so far
- Oct 29, 2024QTS began construction on the campus.
- April 2026The third building was topped out.
Local votes and rules
๐ค Agreement with the company
Eagle Mountain's Redevelopment Agency approved tax-sharing deals for the Sweetwater #4 Community Reinvestment Area, which covers about 567 acres south of Meta's data center for a multi-billion-dollar expansion. Part of the new property taxes will go back to the area for roads, pipes and other infrastructure. Deals with the Alpine School District (Nov 18, 2025) and Utah County (amended Dec 2, 2025) were approved. On Oct 21, 2025 the agency also began planning a Sweetwater #5 area, 523 acres west of Meta, for more data center building, and the city council took up a new development agreement with Meta's company Stadion LLC.
An aerial photo of the area.
Where this comes from
- QTS begins construction on new datacenter campus in Eagle Mountain ยท Eagle Mountain City ยท Oct 29, 2024
- Final beam placed on third data center in Eagle Mountain ยท ABC4 ยท April 2026
- Tracking AI data centers in Utah (map) ยท ABC4 ยท 2026