Approved, not built yetBig (AI-size): 151 acres

Jones Road data center (former paper mill)

Also called: LightHouse Data Centers Spartanburg, 300 Jones Road

A developer wants to build a 200,000-square-foot data center at a former paper mill on Jones Road. The county turned it down in June 2026, and the zoning appeals board agreed in August. In October 2026 County Council changed course and started approving a development agreement, which allows smaller data centers under the county's pause.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Spartanburg County Council (for land outside city and town limits).

Where things stand: Approved, not built yet County Council gave final approval to the development agreement on Nov. 16, 2026. No report yet of construction starting.

  • Nov 17, 2026: Our records now list Jones Road data center (former paper mill) as approved Source
  • Sept 21, 2026: Unincorporated Spartanburg County, Spartanburg County: moratorium adopted Source

❓ 1 open question about it: see below.

Last checked Nov 17, 2026.

🕒 Latest update (Nov 16, 2026): Spartanburg County Council approved the 300 Jones Road Associates development agreement on third and final reading. Reports describe up to 65 megawatts on about 137 acres of the former R.R. Donnelley property, $1.5 billion and 25 jobs.

What we know

  • 📍 Where300 Jones Road (geocoded with the Census geocoder), Unincorporated Spartanburg County, Spartanburg County
  • 🏢 CompanyJones Road Associates
  • 🌳 Size151 acres
  • ⚡ Power it needs60 megawatts (about as much as 48,000 homes)
  • 💵 Cost$1.5 billion
  • 💸 Tax breaksNo fee-in-lieu-of-tax deal. The agreement has the company pay the county $9 million over six years for things like job training and affordable housing, and invest at least $100 million.
  • 👷 Jobs promised25

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the site at 300 Jones Road or 430 Jones Road? News reports give both addresses. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • June 2026
      Spartanburg County planning staff denied the 200,000-square-foot data center, citing the county's land rules and a proposed moratorium.
    • Aug 25, 2026
      The county Board of Zoning Appeals voted unanimously to uphold the denial.
    • Oct 19, 2026
      Spartanburg County Council passed the first of three readings of a development agreement for the 60-megawatt Jones Road data center. It requires at least $100 million in investment and 25 jobs, a noise study, and light, glare and landscaping plans. The company says it plans to invest $1.5 billion and use power from the grid.
    • Nov 3, 2026
      Spartanburg County Council passed the Jones Road development agreement (300 Jones Road Associates) on second reading, 4-1. Reports describe a 65-megawatt facility and a $1.5 billion investment.
    • Nov 16, 2026
      Spartanburg County Council approved the 300 Jones Road Associates development agreement on third and final reading. Reports describe up to 65 megawatts on about 137 acres of the former R.R. Donnelley property, $1.5 billion and 25 jobs.

    Local votes and rules

    ⚖️ Court case

    A judge threw out a neighbors' group lawsuit against Spartanburg County over permits for the Valara (NorthMark) data center. The judge said they should have appealed to the Board of Zoning Appeals first. The ruling did not decide if the project breaks county rules. The group says it will appeal.

    Oct 2026

    ⏸️ Pause on new data centers

    Spartanburg County Council voted 5-1 for a one-year freeze on new data centers bigger than 65 megawatts. Applications were already on hold since the first vote on June 22. Projects already approved, like the Valara (NorthMark) site, are not affected.

    Sept 21, 2026

    ✋ Turned down

    The county zoning appeals board voted unanimously to uphold staff's rejection of a 200,000-square-foot, 60-megawatt data center at the old paper mill site on Jones Road. Staff found code problems and said they could not take the application while the moratorium was pending.

    Aug 25, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something