AIB data center at former crypto mine (Tyger River Industrial Park)
Also called: AIB CLT1, AIB Data Centers, BV Power Alpha, BlockchAIn Digital Infrastructure
AIB Data Centers wants to turn its former bitcoin mine in the Tyger River Industrial Park into a 50-megawatt AI data center for Nebius. It would buy power from the utility rather than make its own. The company says it would use far less water than the mine did. The county's pause on data centers allows projects this size if they sign a development agreement with the county.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Spartanburg County Council (for land outside city and town limits).
Where things stand: Approved, not built yet County Council gave final approval to the development agreement on Nov. 16, 2026. Three more AIB agreements (CLT2, CLT3, CLT4) for the same industrial park passed a first reading that night.
- Nov 17, 2026: Our records now list AIB data center at former crypto mine (Tyger River Industrial Park) as approved Source
❓ 3 open questions about it: see below.
Last checked Nov 17, 2026.
🕒 Latest update (Nov 16, 2026): Spartanburg County Council approved the AIB CLT1 development agreement on third and final reading (50 megawatts, $1.2 billion, 28 jobs). The same night, three more AIB agreements (CLT2, CLT3 and CLT4) at Tyger River Industrial Park passed a first reading. Their size was not reported.
What we know
- 📍 Where389 Tyger River Industrial Drive, Moore (Tyger River Industrial Park), Moore, Spartanburg County
- 🏢 CompanyAIB Data Centers (AIB CLT1 LLC)
- 🏛️ Owned byAIB Data Centers (formerly BlockchAIn Digital Infrastructure)
- 👤 Built forNebius
- 🌳 Size16 acres
- ⚡ Power it needs50 megawatts (about as much as 40,000 homes)
- 🔌 Where the power comes fromBuys power from the local utility under a 15-year deal for 65 megawatts; no power plant on site except emergency backup.
- 💵 Cost$1.2 billion
- 💸 Tax breaksThe company gave up the tax deal the old crypto mine got in 2022, and the county accepted. The draft agreement calls for $12.6 million in community payments over 12 years.
- 👷 Jobs promised28
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which utility will supply the 65 megawatts, and are new power lines needed? 🙋 I'll find out ·
- How many diesel backup generators will the data center have? 🙋 I'll find out ·
- How big are the three newer AIB agreements (CLT2, CLT3, CLT4) at Tyger River Industrial Park, and when are their next votes? 🙋 I'll find out ·
What happened so far
- 2022A cryptocurrency mine started up at the site with a county tax deal.
- June 5, 2026The 40-megawatt bitcoin mining operation was shut off, according to the company's filing.
- Sept 30, 2026AIB announced a 12-year deal to lease 50 megawatts of data center space to the AI company Nebius.
- Oct 13, 2026News reports said AIB plans to turn the former crypto mine into an AI data center, small enough (under 65 megawatts) to qualify for an exception to the county's data center pause.
- Nov 3, 2026At a special meeting, Spartanburg County Council passed the AIB development agreement on second reading, 4-1. It caps the site at 50 megawatts of computing power and 65 megawatts in total. Residents said site plans were missing; the county said they would be posted before the final vote.
- Nov 16, 2026Spartanburg County Council approved the AIB CLT1 development agreement on third and final reading (50 megawatts, $1.2 billion, 28 jobs). The same night, three more AIB agreements (CLT2, CLT3 and CLT4) at Tyger River Industrial Park passed a first reading. Their size was not reported.
Local votes and rules
⚖️ Court case
A judge threw out a neighbors' group lawsuit against Spartanburg County over permits for the Valara (NorthMark) data center. The judge said they should have appealed to the Board of Zoning Appeals first. The ruling did not decide if the project breaks county rules. The group says it will appeal.
⏸️ Pause on new data centers
Spartanburg County Council voted 5-1 for a one-year freeze on new data centers bigger than 65 megawatts. Applications were already on hold since the first vote on June 22. Projects already approved, like the Valara (NorthMark) site, are not affected.
✋ Turned down
The county zoning appeals board voted unanimously to uphold staff's rejection of a 200,000-square-foot, 60-megawatt data center at the old paper mill site on Jones Road. Staff found code problems and said they could not take the application while the moratorium was pending.
Drag the slider to compare the land before and now.
Where this comes from
- New data center planned to replace crypto mining facility in Spartanburg County · Post and Courier · Oct 13, 2026
- AIB plans 50MW AI data center at former Spartanburg cryptomine to serve Nebius (republished from DCD) · DatacenterDynamics / BeBeez · Oct 29, 2026
- Spartanburg County Council approves preliminary NorthMark data center development agreement · Post and Courier · Oct 23, 2026
- Tyger River Industrial Drive (street location, OpenStreetMap via Photon) · OpenStreetMap · Nov 3, 2026
- Spartanburg OKs three data center deals at election day meeting · South Carolina Public Radio · Nov 5, 2026
- 3 Spartanburg County data center projects move closer to approval · FOX Carolina · Nov 4, 2026
- Spartanburg County Council approves three data center agreements, advances three more · WYFF · Nov 16, 2026