Built & running
Amazon PDX138 data center campus, Hermiston
Also called: PDX138
Amazon's first Hermiston campus opened in 2024. Under a 15-year tax deal, Amazon pays set yearly amounts and fees instead of full property taxes. The city says the deal ends in 2040.
Where things stand: Got its occupancy certificate in July 2024 and is operating.
๐ Latest update (Nov 2025): Amazon made its first annual enterprise zone payment of $2.65 million.
What we know
- ๐ Wherein the Greater Hermiston Enterprise Zone, Umatilla County
- ๐ข CompanyAmazon Data Services, Inc.
- ๐๏ธ Owned byAmazon
- ๐ค Built forAmazon (AWS)
- ๐ธ Tax breaks15-year enterprise zone deal: Amazon pays at least $2 million a year plus fees instead of full property tax, and a one-time $5 million community payment.
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is PDX138 inside Hermiston city limits or in unincorporated Umatilla County? ๐ I'll find out
- How much water and power does PDX138 use? ๐ I'll find out
What happened so far
- July 2024Campus received its certificate of occupancy.
- Nov 2025Amazon made its first annual enterprise zone payment of $2.65 million.
๐ฐ๏ธ See it from above
An aerial photo of the area.
Photos: USGS The National Map.
Where this comes from
- Greater Hermiston Enterprise Zone ยท City of Hermiston
- Hermiston annexes land for hyperscale data centers ยท OPB ยท Sept 10, 2025
See something wrong? Tell us and we'll fix it.