Project Clydesdale data center campus near Owasso
Also called: Project Clydesdale, Google Tulsa County campus
Beale Infrastructure is building a 506-acre data center campus for Google on county land west of Owasso. It started in Oct 2025 and is valued at $1 billion for the first phase. Peak water demand was reported at 5–6 million gallons a day.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Tulsa County Commissioners (for land outside city and town limits).
Where things stand: Being built Ground broken Oct 2025; Google named as the user in Aug 2026. First phase due about 2027.
❓ 2 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (Aug 20, 2026): Google said it is the company behind Project Clydesdale.
What we know
- 📍 WhereNorth of E 76th St N, east of N Yale Ave, south of E 86th St N and west of N Sheridan Rd, near Cherokee Industrial Park, west of Owasso, Unincorporated Tulsa County, Tulsa County
- 🏢 CompanyBeale Infrastructure
- 👤 Built forGoogle
- 🌳 Size506 acres
- 🔌 Where the power comes fromPSO grid; developer is paying for a new substation
- 🗼 New power linesYes
- 💧 WaterWashington County Rural Water District No. 3 (1.5 miles of new water lines)
- 💵 Cost$1 billion
- 💸 Tax breaksTulsa County approved tax exemptions; the project is projected to pay about $2 million a year to the county, Owasso schools and others.
- 👷 Jobs promised100
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is the 5–6 million gallons a day peak water figure still correct, and where does that water come from? 🙋 I'll find out ·
- How many megawatts will the campus use? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the site location: news reports put the campus between E 76th St N, N Yale Ave, E 86th St N and N Sheridan Rd. Recent satellite images show a large construction site in the south part of that block. The pin is in the middle of the construction.
What happened so far
- Sept 2025Tulsa County Commissioners approved the project.
- Oct 30, 2025Beale Infrastructure broke ground on the $1 billion campus.
- Aug 20, 2026Google said it is the company behind Project Clydesdale.
Local votes and rules
✅ Approved
Tulsa County commissioners approved tax breaks for the Project Clydesdale data center west of Owasso. Ground was broken in October 2025; Google later said it is the company behind it.
Drag the slider to compare the land before and now.
Where this comes from
- Developers break ground on $1B data center near Tulsa · The Tulsa Flyer · Oct 30, 2025
- Google data center campus in Tulsa County · News 9 · Aug 20, 2026
- In-depth: data center proposals across Green Country · KJRH 2 News
- Census geocoder: 7600 N Yale Ave (SW corner of the block) · US Census Bureau · Oct 8, 2026
- Census geocoder: 8600 N Sheridan Rd (NE corner of the block) · US Census Bureau · Oct 8, 2026